Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2001 |
Principal Product | Electronics |
NAICS | n/a |
SIC | 3661 - Telephone And Telegraph Apparatus |
Sales | $50,000,000-$100,000,000 |
# of Employees | 249 |
Plant Area (Sq.Ft.) | 104,000 |
Annual Production | 1,500 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $185,512 | 2,419,624 | kWh | $0.08 |
Electricity Demand | $7,736 | 776 | kW-months/year | $9.97 |
Natural Gas | $30,586 | 3,404 | MMBtu | $8.99 |
TOTAL ENERGY COSTS | $223,834 | |||
RECOMMENDED SAVINGS* | $25,303 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,749 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.1162 USE LESS WASTEFUL PACKAGING |
Savings: $1,700 Cost: - |
- | - | - | - | - | - | $1,700 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,700 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $561 Cost: $640 |
$423 | 6,048 | $138 | 15 | - | - | - | - |
$423 6,048 kWh |
$138 15 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,150 Cost: $4,410 |
$4,672 | 60,678 | $1,478 | 123 | - | - | - | - |
$4,672 60,678 kWh |
$1,478 123 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $9,638 Cost: - |
$9,638 | 125,174 | - | - | - | - | - | - |
$9,638 125,174 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $961 Cost: $1,250 |
$961 | 12,480 | - | - | - | - | - | - |
$961 12,480 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $6,293 Cost: $41,225 |
- | - | - | - | $6,293 | 701 | - | - |
- - kWh |
- - kW-months/year |
$6,293 701 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,303 Cost: $47,525 |
$15,694 | 204,380 | $1,616 | 138 | $6,293 | 701 | $1,700 | - | $15,694 204,380 kWh |
$1,616 138 kW-months/year |
$6,293 701 MMBtu |
$1,700 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,749 Cost: $5,660 |
$15,271 | 198,332 | $1,478 | 123 | - | - | - | - | $15,271 198,332 kWh |
$1,478 123 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) |