Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2002 |
Principal Product | Printing Material |
NAICS | n/a |
SIC | 2761 - Manifold Business Forms |
Sales | $5,000,000-$10,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 44,000 |
Annual Production | 8,000,000 Pounds |
Production Hrs. Annual | 4,160 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $149,037 | 1,258,165 | kWh | $0.12 |
Electricity Demand | $31,667 | 3,958 | kW-months/year | $8.00 |
Natural Gas | $6,427 | 629 | MMBtu | $10.22 |
TOTAL ENERGY COSTS | $187,131 | |||
RECOMMENDED SAVINGS* | $23,471 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,218 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,365 Cost: - |
$2,749 | 29,564 | $616 | 76 | - | - | - | - |
$2,749 29,564 kWh |
$616 76 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $929 Cost: $1,000 |
$619 | 6,654 | $310 | 39 | - | - | - | - |
$619 6,654 kWh |
$310 39 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $3,820 Cost: - |
$3,820 | 32,254 | - | - | - | - | - | - |
$3,820 32,254 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,018 Cost: $920 |
$416 | 4,474 | - | - | $2,602 | 255 | - | - |
$416 4,474 kWh |
- - kW-months/year |
$2,602 255 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $4,000 Cost: - |
- | - | - | - | - | - | $4,000 | 57,652 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,000 57,652 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR |
Savings: $7,306 Cost: $10,000 |
- | - | - | - | $7,306 | 716 | - | - |
- - kWh |
- - kW-months/year |
$7,306 716 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,033 Cost: $3,718 |
$862 | 9,266 | $171 | 21 | - | - | - | - |
$862 9,266 kWh |
$171 21 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,471 Cost: $15,638 |
$8,466 | 82,212 | $1,097 | 136 | $9,908 | 971 | $4,000 | 57,652 | $8,466 82,212 kWh |
$1,097 136 kW-months/year |
$9,908 971 MMBtu |
$4,000 57,652 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,218 Cost: $3,718 |
$7,431 | 71,084 | $787 | 97 | - | - | - | - | $7,431 71,084 kWh |
$787 97 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) |