IAC Assessment: LE0204
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LE0204
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Lehigh University
Assessment Year 2005
Principal Product Asphalt Products
NAICS 324122 - Asphalt Shingle and Coating Materials Manufacturing
SIC 2952 - Asphalt Felts And Coatings
Sales $10,000,000-$50,000,000
# of Employees 15
Plant Area (Sq.Ft.) 70,000
Annual Production 30,000 Tons
Production Hrs. Annual 4,160
Location (State) NJ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $52,350 928,200 kWh $0.06
Electricity Demand $34,987 7,762 kW-months/year $4.51
Natural Gas $277,333 36,898 MMBtu $7.52
Fuel Oil #2 $75,757 11,327 MMBtu $6.69
TOTAL ENERGY COSTS $440,427
RECOMMENDED SAVINGS* $46,500 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,631
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Electricity Usage Electricity Demand Natural Gas Fuel Oil #2
$ kWh $ kW-months/year $ MMBtu $ MMBtu
01: 3.6124 BURN WASTE OIL FOR HEAT Savings:
$18,746
Cost:
$3,000
- - - - - - $18,746 2,803 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$18,746
2,803
MMBtu
02: 2.2123 INSULATE FEEDWATER TANK Savings:
$18,286
Cost:
$8,304
- - - - $18,286 2,702 - - -
-
kWh
-
-
kW-months/year
$18,286
2,702
MMBtu
-
-
MMBtu
03: 2.6124 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE Savings:
$4,345
Cost:
$2,750
$4,345 77,584 - - - - - - $4,345
77,584
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$3,339
Cost:
$6,000
- - - - $3,339 444 - - -
-
kWh
-
-
kW-months/year
$3,339
444
MMBtu
-
-
MMBtu
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,784
Cost:
$600
$1,418 25,322 $366 81 - - - - $1,418
25,322
kWh
$366
81
kW-months/year
-
-
MMBtu
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$46,500
Cost:
$20,654
$5,763 102,906 $366 81 $21,625 3,146 $18,746 2,803 $5,763
102,906
kWh
$366
81
kW-months/year
$21,625
3,146
MMBtu
$18,746
2,803
MMBtu
TOTAL IMPLEMENTED Savings:
$22,631
Cost:
$11,054
$4,345 77,584 - - $18,286 2,702 - - $4,345
77,584
kWh
-
-
kW-months/year
$18,286
2,702
MMBtu
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ MMBtu
Electricity Usage Electricity Demand Natural Gas Fuel Oil #2 Electricity Usage Electricity Demand Natural Gas Fuel Oil #2