IAC logo
IAC Assessment: LE0218
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LE0218
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Lehigh University
Assessment Year 2005
Principal Product Cleaning Products
NAICS 325612 - Polish and Other Sanitation Good Manufacturing
SIC 2842 - Polishes And Sanitation Goods
Sales $50,000,000-$100,000,000
# of Employees 49
Plant Area (Sq.Ft.) 142,000
Annual Production 73,000,000 Pounds
Production Hrs. Annual 4,160
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $139,678 2,226,320 kWh $0.06
Electricity Demand $37,303 5,092 kW-months/year $7.33
Natural Gas $146,822 15,952 MMBtu $9.20
TOTAL ENERGY COSTS $323,803
RECOMMENDED SAVINGS* $59,412 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7311 VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE Savings:
$39,290
Cost:
$600
$2,031 32,227 - - $37,259 4,050 $2,031
32,227
kWh
-
-
kW-months/year
$37,259
4,050
MMBtu
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$6,740
Cost:
$3,000
- - $6,740 920 - - -
-
kWh
$6,740
920
kW-months/year
-
-
MMBtu
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$5,249
Cost:
$1,250
- - - - $5,249 571 -
-
kWh
-
-
kW-months/year
$5,249
571
MMBtu
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$3,565
Cost:
$480
$3,565 57,502 - - - - $3,565
57,502
kWh
-
-
kW-months/year
-
-
MMBtu
05: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE Savings:
$3,530
Cost:
$480
$2,293 36,400 $1,237 134 - - $2,293
36,400
kWh
$1,237
134
kW-months/year
-
-
MMBtu
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,038
Cost:
$1,200
$867 13,759 $171 23 - - $867
13,759
kWh
$171
23
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$59,412
Cost:
$7,010
$8,756 139,888 $8,148 1,077 $42,508 4,621 $8,756
139,888
kWh
$8,148
1,077
kW-months/year
$42,508
4,621
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas