Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2006 |
Principal Product | hollow fiber membrane modules |
NAICS | 325220 - Artificial and Synthetic Fibers and Filaments Manufacturing |
SIC | 2824 - Organic Fibers, Noncellulosic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 99 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 5,000 Pieces |
Production Hrs. Annual | 8,736 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $262,545 | 7,314,330 | kWh | $0.04 |
Electricity Demand | $193,392 | 17,673 | kW-months/year | $10.94 |
Natural Gas | $654,101 | 62,659 | MMBtu | $10.44 |
TOTAL ENERGY COSTS | $1,110,038 | |||
RECOMMENDED SAVINGS* | $316,385 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2423 INSTALL WASTE HEAT BOILER TO PRODUCE STEAM |
Savings: $193,808 Cost: $200,000 |
- | - | - | - | - | - | $193,808 | 18,564 |
- - kWh |
- - kW-months/year |
- - $ |
$193,808 18,564 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $28,291 Cost: $86,000 |
$12,905 | 358,445 | $5,386 | 492 | $10,000 | - | - | - |
$12,905 358,445 kWh |
$5,386 492 kW-months/year |
$10,000 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $27,533 Cost: $20,000 |
$14,875 | 413,112 | $12,658 | 1,157 | - | - | - | - |
$14,875 413,112 kWh |
$12,658 1,157 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $27,306 Cost: $200 |
$19,351 | 537,522 | $7,955 | 727 | - | - | - | - |
$19,351 537,522 kWh |
$7,955 727 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7292 LOWER CEILING TO REDUCE CONDITIONED SPACE |
Savings: $18,286 Cost: $50,000 |
$12,901 | 358,351 | $5,385 | 492 | - | - | - | - |
$12,901 358,351 kWh |
$5,385 492 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $8,730 Cost: $2,400 |
$6,197 | 172,140 | $2,533 | 232 | - | - | - | - |
$6,197 172,140 kWh |
$2,533 232 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,824 Cost: $80 |
$4,275 | 118,741 | $2,549 | 233 | - | - | - | - |
$4,275 118,741 kWh |
$2,549 233 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,925 Cost: $2,000 |
$1,825 | 50,684 | $1,100 | 101 | - | - | - | - |
$1,825 50,684 kWh |
$1,100 101 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $995 Cost: $525 |
$995 | 27,631 | - | - | - | - | - | - |
$995 27,631 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,687 Cost: $7,500 |
$637 | 17,680 | $1,050 | 96 | - | - | - | - |
$637 17,680 kWh |
$1,050 96 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $316,385 Cost: $368,705 |
$73,961 | 2,054,306 | $38,616 | 3,530 | $10,000 | - | $193,808 | 18,564 | $73,961 2,054,306 kWh |
$38,616 3,530 kW-months/year |
$10,000 - $ |
$193,808 18,564 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |