Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2007 |
Principal Product | Hardcover and Softcover Books |
NAICS | 323111 - Commercial Printing (except Screen and Books) |
SIC | 2732 - Book Printing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 367 |
Plant Area (Sq.Ft.) | 190,000 |
Annual Production | 19,000,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $348,649 | 8,013,538 | kWh | $0.04 |
Electricity Demand | $165,233 | 17,302 | kW-months/year | $9.55 |
Natural Gas | $90,255 | 9,538 | MMBtu | $9.46 |
Fuel Oil #2 | $102,634 | 9,193 | MMBtu | $11.16 |
TOTAL ENERGY COSTS | $706,771 | |||
RECOMMENDED SAVINGS* | $95,363 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,649 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $29,905 Cost: $50,000 |
$20,066 | 456,005 | $4,185 | 438 | - | - | $5,654 | - |
$20,066 456,005 kWh |
$4,185 438 kW-months/year |
- - MMBtu |
$5,654 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $29,184 Cost: $20,000 |
$12,369 | 281,085 | $5,577 | 584 | $11,238 | 1,007 | - | - |
$12,369 281,085 kWh |
$5,577 584 kW-months/year |
$11,238 1,007 MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $10,625 Cost: $20,000 |
$7,495 | 170,367 | $3,130 | 328 | - | - | - | - |
$7,495 170,367 kWh |
$3,130 328 kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $5,950 Cost: $800 |
$5,950 | 135,233 | - | - | - | - | - | - |
$5,950 135,233 kWh |
- - kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $4,181 Cost: $300 |
$2,950 | 67,033 | $1,231 | 129 | - | - | - | - |
$2,950 67,033 kWh |
$1,231 129 kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,288 Cost: $1,500 |
$1,612 | 36,688 | $676 | 71 | - | - | - | - |
$1,612 36,688 kWh |
$676 71 kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $1,147 Cost: $750 |
$1,147 | 26,068 | - | - | - | - | - | - |
$1,147 26,068 kWh |
- - kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $12,083 Cost: $14,479 |
$8,523 | 193,752 | $3,560 | 373 | - | - | - | - |
$8,523 193,752 kWh |
$3,560 373 kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $95,363 Cost: $107,829 |
$60,112 | 1,366,231 | $18,359 | 1,923 | $11,238 | 1,007 | $5,654 | - | $60,112 1,366,231 kWh |
$18,359 1,923 kW-months/year |
$11,238 1,007 MMBtu |
$5,654 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,649 Cost: $17,829 |
$20,182 | 458,774 | $5,467 | 573 | - | - | - | - | $20,182 458,774 kWh |
$5,467 573 kW-months/year |
- - MMBtu |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Increase in Production |