Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2011 |
Principal Product | Frozen Food |
NAICS | 311411 - Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2053 - Frozen Bakery Products, Except Bread |
Sales | $100,000,000-$500,000,000 |
# of Employees | 329 |
Plant Area (Sq.Ft.) | 233,000 |
Annual Production | 64,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,061,733 | 18,520,951 | kWh | $0.06 |
Electricity Demand | $516,916 | 35,132 | kW-months/year | $14.71 |
Natural Gas | $323,347 | 59,394 | MMBtu | $5.44 |
TOTAL ENERGY COSTS | $1,901,996 | |||
RECOMMENDED SAVINGS* | $541,066 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $42,698 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $404,827 Cost: $2,200,000 |
$957,600 | 16,800,000 | $353,040 | 24,000 | $(-905,813) | (-166,510) | - | - |
$957,600 16,800,000 kWh |
$353,040 24,000 kW-months/year |
$(-905,813) (-166,510) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $48,359 Cost: $25,500 |
$32,319 | 567,003 | $16,040 | 1,090 | - | - | - | - |
$32,319 567,003 kWh |
$16,040 1,090 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $25,842 Cost: $2,500 |
- | - | $25,842 | 1,757 | - | - | - | - |
- - kWh |
$25,842 1,757 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $22,464 Cost: $250 |
$16,097 | 282,408 | - | - | $6,367 | 1,170 | - | - |
$16,097 282,408 kWh |
- - kW-months/year |
$6,367 1,170 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $18,864 Cost: $50,000 |
$5,332 | 93,542 | $2,265 | 158 | $9,267 | 1,703 | $2,000 | - |
$5,332 93,542 kWh |
$2,265 158 kW-months/year |
$9,267 1,703 MMBtu |
$2,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,689 Cost: $40 |
$5,675 | 99,572 | $2,014 | 137 | - | - | - | - |
$5,675 99,572 kWh |
$2,014 137 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $6,281 Cost: $20,000 |
- | - | - | - | $6,281 | 1,154 | - | - |
- - kWh |
- - kW-months/year |
$6,281 1,154 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,370 Cost: $2,000 |
$3,230 | 56,631 | $2,140 | 145 | - | - | - | - |
$3,230 56,631 kWh |
$2,140 145 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,370 Cost: $249 |
- | - | - | - | $1,370 | 252 | - | - |
- - kWh |
- - kW-months/year |
$1,370 252 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $541,066 Cost: $2,300,539 |
$1,020,253 | 17,899,156 | $401,341 | 27,287 | $(-882,528) | (-162,231) | $2,000 | - | $1,020,253 17,899,156 kWh |
$401,341 27,287 kW-months/year |
$(-882,528) (-162,231) MMBtu |
$2,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $42,698 Cost: $50,499 |
$21,429 | 375,950 | $2,265 | 158 | $17,004 | 3,125 | $2,000 | - | $21,429 375,950 kWh |
$2,265 158 kW-months/year |
$17,004 3,125 MMBtu |
$2,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |