Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2011 |
Principal Product | Mltiwall paper bags |
NAICS | 322220 - Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2674 - Bags: Uncoated Paper & Multiwall |
Sales | $10,000,000-$50,000,000 |
# of Employees | 77 |
Plant Area (Sq.Ft.) | 191,000 |
Annual Production | 18,000 Tons |
Production Hrs. Annual | 8,736 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $336,720 | 4,185,800 | kWh | $0.08 |
Electricity Demand | $46,266 | 7,126 | kW-months/year | $6.49 |
Natural Gas | $33,875 | 7,440 | MMBtu | $4.55 |
TOTAL ENERGY COSTS | $416,861 | |||
RECOMMENDED SAVINGS* | $124,577 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,279 Cost: $1,300 |
$4,671 | 58,384 | $608 | 94 | - | - | - | - |
$4,671 58,384 kWh |
$608 94 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,106 Cost: $200 |
$1,820 | 22,751 | $286 | 44 | - | - | - | - |
$1,820 22,751 kWh |
$286 44 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,316 Cost: $2,000 |
- | - | - | - | $2,316 | 509 | - | - |
- - kWh |
- - kW-months/year |
$2,316 509 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,558 Cost: $240 |
$1,402 | 17,529 | $156 | 24 | - | - | - | - |
$1,402 17,529 kWh |
$156 24 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $83,751 Cost: $81,700 |
$80,056 | 953,045 | $3,554 | 570 | - | - | $141 | - |
$80,056 953,045 kWh |
$3,554 570 kW-months/year |
- - MMBtu |
$141 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $24,213 Cost: $52,000 |
$21,974 | 261,591 | $2,239 | 359 | - | - | - | - |
$21,974 261,591 kWh |
$2,239 359 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $887 Cost: $300 |
$887 | 10,562 | - | - | - | - | - | - |
$887 10,562 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,467 Cost: $34,200 |
$3,255 | 40,688 | $725 | 112 | - | - | $487 | - |
$3,255 40,688 kWh |
$725 112 kW-months/year |
- - MMBtu |
$487 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $124,577 Cost: $171,940 |
$114,065 | 1,364,550 | $7,568 | 1,203 | $2,316 | 509 | $628 | - | $114,065 1,364,550 kWh |
$7,568 1,203 kW-months/year |
$2,316 509 MMBtu |
$628 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |