Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2011 |
Principal Product | Cleaning and Sanitization Products |
NAICS | 325611 - Soap and Other Detergent Manufacturing |
SIC | 2841 - Soap And Other Detergents |
Sales | $10,000,000-$50,000,000 |
# of Employees | 52 |
Plant Area (Sq.Ft.) | 49,500 |
Annual Production | 75,000 Thousand Gallons |
Production Hrs. Annual | 2,080 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $68,859 | 843,072 | kWh | $0.08 |
Electricity Demand | $20,010 | 2,235 | kW-months/year | $8.95 |
Natural Gas | $4,267 | 315 | MMBtu | $13.55 |
TOTAL ENERGY COSTS | $93,136 | |||
RECOMMENDED SAVINGS* | $11,484 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,515 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,515 Cost: $1,000 |
$5,152 | 62,833 | $2,363 | 264 | - | - |
$5,152 62,833 kWh |
$2,363 264 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $3,000 Cost: $8,500 |
$975 | 11,896 | $618 | 69 | $1,407 | - |
$975 11,896 kWh |
$618 69 kW-months/year |
$1,407 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $781 Cost: $8,625 |
$435 | 5,304 | $277 | 31 | $69 | - |
$435 5,304 kWh |
$277 31 kW-months/year |
$69 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $188 Cost: $175 |
$188 | 2,288 | - | - | - | - |
$188 2,288 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,484 Cost: $18,300 |
$6,750 | 82,321 | $3,258 | 364 | $1,476 | - | $6,750 82,321 kWh |
$3,258 364 kW-months/year |
$1,476 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,515 Cost: $9,500 |
$6,127 | 74,729 | $2,981 | 333 | $1,407 | - | $6,127 74,729 kWh |
$2,981 333 kW-months/year |
$1,407 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost |