Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2012 |
Principal Product | Valves |
NAICS | 332911 - Industrial Valve Manufacturing |
SIC | 3491 - Industrial Valves |
Sales | $10,000,000-$50,000,000 |
# of Employees | 54 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 12,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $51,548 | 716,000 | kWh | $0.07 |
Electricity Demand | $8,213 | 1,821 | kW-months/year | $4.51 |
Natural Gas | $19,012 | 1,626 | MMBtu | $11.69 |
TOTAL ENERGY COSTS | $78,773 | |||
RECOMMENDED SAVINGS* | $30,821 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $28,551 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,093 Cost: $14,250 |
$9,902 | 137,530 | $1,191 | 264 | - | - |
$9,902 137,530 kWh |
$1,191 264 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,634 Cost: $1,800 |
- | - | - | - | $1,634 | 141 |
- - kWh |
- - kW-months/year |
$1,634 141 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $10,292 Cost: $12,880 |
$9,187 | 127,593 | $1,105 | 245 | - | - |
$9,187 127,593 kWh |
$1,105 245 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $414 Cost: $525 |
$369 | 5,125 | $45 | 10 | - | - |
$369 5,125 kWh |
$45 10 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $94 Cost: $500 |
- | - | - | - | $94 | 8 |
- - kWh |
- - kW-months/year |
$94 8 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,166 Cost: $3,152 |
$122 | 1,692 | $7,045 | 1,562 | - | - |
$122 1,692 kWh |
$7,045 1,562 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $129 Cost: $109 |
- | - | - | - | $129 | 11 |
- - kWh |
- - kW-months/year |
$129 11 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,821 Cost: $33,216 |
$19,580 | 271,940 | $9,385 | 2,081 | $1,857 | 160 | $19,580 271,940 kWh |
$9,385 2,081 kW-months/year |
$1,857 160 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $28,551 Cost: $30,282 |
$19,211 | 266,815 | $9,340 | 2,071 | - | - | $19,211 266,815 kWh |
$9,340 2,071 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |