Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2015 |
Principal Product | High purity gases |
NAICS | 325120 - Industrial Gas Manufacturing |
SIC | 2813 - Industrial Gases |
Sales | $5,000,000-$10,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 20,000 |
Annual Production | 56,400 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $225,906 | 2,622,780 | kWh | $0.09 |
Electricity Demand | $32,155 | 4,877 | kW-months/year | $6.59 |
Electricity Fees | $39,615 | - | $ | - |
Natural Gas | $42,874 | 3,725 | MMBtu | $11.51 |
TOTAL ENERGY COSTS | $340,550 | |||
RECOMMENDED SAVINGS* | $78,226 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $903 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $21,570 Cost: $12,000 |
$19,672 | 228,736 | $1,898 | 285 | - | - | - | - |
$19,672 228,736 kWh |
$1,898 285 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $903 Cost: $525 |
$692 | 8,044 | $211 | 32 | - | - | - | - |
$692 8,044 kWh |
$211 32 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,761 Cost: $2,125 |
$241 | 2,797 | - | - | $2,521 | 219 | - | - |
$241 2,797 kWh |
- - kW-months/year |
$2,521 219 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $13,857 Cost: $14,800 |
$11,972 | 139,213 | $1,885 | 286 | - | - | - | - |
$11,972 139,213 kWh |
$1,885 286 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $369 Cost: $884 |
$323 | 3,756 | $46 | 7 | - | - | - | - |
$323 3,756 kWh |
$46 7 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $205 Cost: $600 |
$205 | 2,387 | - | - | - | - | - | - |
$205 2,387 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,132 Cost: $3,725 |
$987 | 11,482 | $145 | 22 | - | - | - | - |
$987 11,482 kWh |
$145 22 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $29,538 Cost: $129,220 |
$7,544 | 87,725 | - | - | - | - | $21,994 | - |
$7,544 87,725 kWh |
- - kW-months/year |
- - MMBtu |
$21,994 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,157 Cost: $27,450 |
$5,366 | 62,400 | $791 | 120 | - | - | - | - |
$5,366 62,400 kWh |
$791 120 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,733 Cost: $8,550 |
$1,465 | 17,035 | $268 | 41 | - | - | - | - |
$1,465 17,035 kWh |
$268 41 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $78,226 Cost: $199,879 |
$48,468 | 563,575 | $5,243 | 793 | $2,521 | 219 | $21,994 | - | $48,468 563,575 kWh |
$5,243 793 kW-months/year |
$2,521 219 MMBtu |
$21,994 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $903 Cost: $525 |
$692 | 8,044 | $211 | 32 | - | - | - | - | $692 8,044 kWh |
$211 32 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |