Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2017 |
Principal Product | Steel storage Cabinet |
NAICS | 337214 - Office Furniture (except Wood) Manufacturing |
SIC | 2522 - Office Furniture, Except Wood |
Sales | $10,000,000-$50,000,000 |
# of Employees | 37 |
Plant Area (Sq.Ft.) | 160,000 |
Annual Production | 2,000 Tons |
Production Hrs. Annual | 4,420 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $80,084 | 1,182,750 | kWh | $0.07 |
Electricity Demand | $20,389 | 5,009 | kW-months/year | $4.07 |
Electricity Fees | $10,657 | - | $ | - |
Natural Gas | $70,370 | 14,289 | MMBtu | $4.92 |
TOTAL ENERGY COSTS | $181,500 | |||
RECOMMENDED SAVINGS* | $55,218 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,498 Cost: $1,000 |
$4,030 | 59,262 | $468 | 115 | - | - |
$4,030 59,262 kWh |
$468 115 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $18,942 Cost: $7,500 |
- | - | - | - | $18,942 | 3,850 |
- - kWh |
- - kW-months/year |
$18,942 3,850 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,145 Cost: $1,500 |
- | - | - | - | $2,145 | 436 |
- - kWh |
- - kW-months/year |
$2,145 436 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $892 Cost: $1,200 |
$725 | 10,659 | $167 | 41 | - | - |
$725 10,659 kWh |
$167 41 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $772 Cost: $1,100 |
$137 | 2,009 | - | - | $635 | 129 |
$137 2,009 kWh |
- - kW-months/year |
$635 129 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,605 Cost: $12,500 |
$5,176 | 76,124 | $1,429 | 351 | - | - |
$5,176 76,124 kWh |
$1,429 351 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,711 Cost: $33,950 |
$14,703 | 216,216 | $3,008 | 739 | - | - |
$14,703 216,216 kWh |
$3,008 739 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,334 Cost: $5,100 |
$878 | 12,918 | $456 | 112 | - | - |
$878 12,918 kWh |
$456 112 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $566 Cost: $2,525 |
$476 | 6,993 | $90 | 22 | - | - |
$476 6,993 kWh |
$90 22 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,753 Cost: $8,500 |
$1,570 | 23,082 | $183 | 45 | - | - |
$1,570 23,082 kWh |
$183 45 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,218 Cost: $74,875 |
$27,695 | 407,263 | $5,801 | 1,425 | $21,722 | 4,415 | $27,695 407,263 kWh |
$5,801 1,425 kW-months/year |
$21,722 4,415 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |