Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2017 |
Principal Product | Rubber Seals |
NAICS | 339991 - Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053 - Gaskets, Packing And Sealing Devices |
Sales | $10,000,000-$50,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 62,000 |
Annual Production | 6,702,219 Units |
Production Hrs. Annual | 6,000 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $200,165 | 3,268,759 | kWh | $0.06 |
Electricity Demand | $42,753 | 7,863 | kW-months/year | $5.44 |
Electricity Fees | $60,517 | - | $ | - |
Natural Gas | $27,100 | 2,356 | MMBtu | $11.50 |
TOTAL ENERGY COSTS | $330,535 | |||
RECOMMENDED SAVINGS* | $84,476 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,765 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $4,712 Cost: $20 |
- | - | - | - | $4,712 | - |
- - kWh |
- - kW-months/year |
$4,712 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,114 Cost: $20 |
$994 | 16,293 | $120 | 22 | - | - |
$994 16,293 kWh |
$120 22 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,738 Cost: $1,000 |
$6,004 | 98,422 | $734 | 135 | - | - |
$6,004 98,422 kWh |
$734 135 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $57,323 Cost: $15,000 |
$42,700 | 700,000 | $14,623 | 2,688 | - | - |
$42,700 700,000 kWh |
$14,623 2,688 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $831 Cost: $1,000 |
$739 | 12,113 | $92 | 17 | - | - |
$739 12,113 kWh |
$92 17 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,845 Cost: $16,000 |
$8,164 | 133,832 | $1,681 | 309 | - | - |
$8,164 133,832 kWh |
$1,681 309 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $780 Cost: $2,067 |
$666 | 10,920 | $114 | 21 | - | - |
$666 10,920 kWh |
$114 21 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,133 Cost: $9,520 |
$2,660 | 43,603 | $473 | 87 | - | - |
$2,660 43,603 kWh |
$473 87 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $84,476 Cost: $44,627 |
$61,926 | 1,015,183 | $17,838 | 3,279 | $4,712 | - | $61,926 1,015,183 kWh |
$17,838 3,279 kW-months/year |
$4,712 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,765 Cost: $12,607 |
$10,324 | 169,238 | $1,442 | 265 | - | - | $10,324 169,238 kWh |
$1,442 265 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost |