Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Lehigh University |
---|---|
Assessment Year | 2018 |
Principal Product | PTFE & Waxes |
NAICS | 325998 - All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899 - Chemical Preparations, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 53 |
Plant Area (Sq.Ft.) | 114,200 |
Annual Production | 500,000 Units |
Production Hrs. Annual | 5,610 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $510,915 | 4,564,575 | kWh | $0.11 |
Electricity Demand | $114,448 | 16,834 | kW-months/year | $6.80 |
Electricity Fees | $48,982 | - | $ | - |
Natural Gas | $82,985 | 8,467 | MMBtu | $9.80 |
TOTAL ENERGY COSTS | $757,330 | |||
RECOMMENDED SAVINGS* | $32,791 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,590 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $10,236 Cost: $500 |
$9,148 | 81,678 | $1,088 | 160 | - | - |
$9,148 81,678 kWh |
$1,088 160 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,449 Cost: $150 |
$332 | 2,966 | $1,117 | 114 | - | - |
$332 2,966 kWh |
$1,117 114 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,024 Cost: $1,500 |
$8,956 | 79,968 | $1,068 | 157 | - | - |
$8,956 79,968 kWh |
$1,068 157 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,764 Cost: $1,200 |
- | - | - | - | $1,764 | 180 |
- - kWh |
- - kW-months/year |
$1,764 180 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $744 Cost: $600 |
$594 | 5,307 | $150 | 22 | - | - |
$594 5,307 kWh |
$150 22 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,163 Cost: $3,019 |
$1,959 | 17,491 | $204 | 30 | - | - |
$1,959 17,491 kWh |
$204 30 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,058 Cost: $6,563 |
$3,058 | 27,300 | - | - | - | - |
$3,058 27,300 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $3,352 Cost: $22,000 |
- | - | - | - | $3,352 | 342 |
- - kWh |
- - kW-months/year |
$3,352 342 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,791 Cost: $35,532 |
$24,048 | 214,710 | $3,627 | 483 | $5,116 | 522 | $24,048 214,710 kWh |
$3,627 483 kW-months/year |
$5,116 522 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,590 Cost: $9,863 |
$12,609 | 112,575 | $1,218 | 179 | $1,764 | 180 | $12,609 112,575 kWh |
$1,218 179 kW-months/year |
$1,764 180 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |