Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisiana, Lafayette |
---|---|
Assessment Year | 2002 |
Principal Product | Rubber products |
NAICS | n/a |
SIC | 2822 - Synthetic Rubber |
Sales | $5,000,000-$10,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 97,000 |
Annual Production | 3,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $143,275 | 1,964,720 | kWh | $0.07 |
Electricity Fees | $5,331 | - | $ | - |
Natural Gas | $33,841 | 2,885 | MMBtu | $11.73 |
TOTAL ENERGY COSTS | $189,779 | |||
RECOMMENDED SAVINGS* | $153,532 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,685 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,548 Cost: - |
$1,488 | 20,405 | $60 | - | - | - | - | - |
$1,488 20,405 kWh |
$60 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,068 Cost: $210 |
$1,027 | 14,082 | $41 | - | - | - | - | - |
$1,027 14,082 kWh |
$41 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,100 Cost: $364 |
$1,058 | 14,511 | $42 | - | - | - | - | - |
$1,058 14,511 kWh |
$42 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $450 Cost: $90 |
$433 | 5,932 | $17 | - | - | - | - | - |
$433 5,932 kWh |
$17 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $167 Cost: $30 |
$161 | 2,213 | $6 | - | - | - | - | - |
$161 2,213 kWh |
$6 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $142,800 Cost: $377,995 |
- | - | - | - | - | - | $142,800 | - |
- - kWh |
- - $ |
- - lb |
$142,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5218 REUSE / RECYCLE/ SELL RUBBER PRODUCTS |
Savings: $6,399 Cost: - |
- | - | - | - | $6,399 | 768 | - | - |
- - kWh |
- - $ |
$6,399 768 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $153,532 Cost: $378,689 |
$4,167 | 57,143 | $166 | - | $6,399 | 768 | $142,800 | - | $4,167 57,143 kWh |
$166 - $ |
$6,399 768 lb |
$142,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,685 Cost: $330 |
$1,621 | 22,227 | $64 | - | - | - | - | - | $1,621 22,227 kWh |
$64 - $ |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Primary Product | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Primary Product |