Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisiana, Lafayette |
---|---|
Assessment Year | 2002 |
Principal Product | Asphalt and Concrete |
NAICS | n/a |
SIC | 2951 - Asphalt Paving Mixtures And Blocks |
Sales | $5,000,000-$10,000,000 |
# of Employees | 13 |
Plant Area (Sq.Ft.) | 508,000 |
Annual Production | 250,000 Tons |
Production Hrs. Annual | 4,368 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $71,729 | 1,049,714 | kWh | $0.07 |
Electricity Demand | $31,554 | 5,643 | kW-months/year | $5.59 |
Electricity Fees | $3,511 | - | $ | - |
Natural Gas | $336,131 | 59,582 | MMBtu | $5.64 |
TOTAL ENERGY COSTS | $442,925 | |||
RECOMMENDED SAVINGS* | $57,896 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,456 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $50,444 Cost: $27,801 |
- | - | - | - | - | - | $50,444 | 8,600 |
- - kWh |
- - kW-months/year |
- - $ |
$50,444 8,600 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,446 Cost: $1,992 |
- | - | - | - | - | - | $2,446 | 417 |
- - kWh |
- - kW-months/year |
- - $ |
$2,446 417 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,946 Cost: $90 |
$1,871 | 26,752 | - | - | $75 | - | - | - |
$1,871 26,752 kWh |
- - kW-months/year |
$75 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,550 Cost: $104 |
$1,244 | 18,211 | $246 | 44 | $60 | - | - | - |
$1,244 18,211 kWh |
$246 44 kW-months/year |
$60 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,123 Cost: $182 |
$901 | 13,179 | $179 | 32 | $43 | - | - | - |
$901 13,179 kWh |
$179 32 kW-months/year |
$43 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $387 Cost: $26 |
$311 | 4,553 | $61 | 11 | $15 | - | - | - |
$311 4,553 kWh |
$61 11 kW-months/year |
$15 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $57,896 Cost: $30,195 |
$4,327 | 62,695 | $486 | 87 | $193 | - | $52,890 | 9,017 | $4,327 62,695 kWh |
$486 87 kW-months/year |
$193 - $ |
$52,890 9,017 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,456 Cost: $298 |
$3,083 | 44,484 | $240 | 43 | $133 | - | - | - | $3,083 44,484 kWh |
$240 43 kW-months/year |
$133 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |