Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Loyola Marymount University |
---|---|
Assessment Year | 2001 |
Principal Product | compressed gas cylinders |
NAICS | n/a |
SIC | 3463 - Nonferrous Forgings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 74,000 |
Annual Production | 590,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $172,336 | 2,814,294 | kWh | $0.06 |
Electricity Demand | $107,512 | 8,844 | kW-months/year | $12.16 |
Electricity Fees | $5,976 | - | $ | - |
Natural Gas | $164,633 | 29,887 | MMBtu | $5.51 |
TOTAL ENERGY COSTS | $450,457 | |||
RECOMMENDED SAVINGS* | $55,410 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,524 |
#|Description |
Savings Cost |
Status | Natural Gas | Personnel Changes | Administrative Changes | Increase in Production | Natural Gas | Personnel Changes | Administrative Changes | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $8,902 Cost: $8,000 |
$8,902 | 1,108 | - | - | - | - | - | - |
$8,902 1,108 MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $724 Cost: $350 |
$1,504 | 201 | $(-780) | - | - | - | - | - |
$1,504 201 MMBtu |
$(-780) - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $5,910 Cost: $11,800 |
- | - | - | - | $5,910 | - | - | - |
- - MMBtu |
- - $ |
$5,910 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $7,800 Cost: $2,250 |
- | - | $7,800 | - | - | - | - | - |
- - MMBtu |
$7,800 - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $30,900 Cost: $8,000 |
- | - | - | - | - | - | $30,900 | - |
- - MMBtu |
- - $ |
- - $ |
$30,900 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $1,174 Cost: $500 |
- | - | - | - | - | - | $1,174 | - |
- - MMBtu |
- - $ |
- - $ |
$1,174 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,410 Cost: $30,900 |
$10,406 | 1,309 | $7,020 | - | $5,910 | - | $32,074 | - | $10,406 1,309 MMBtu |
$7,020 - $ |
$5,910 - $ |
$32,074 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,524 Cost: $2,600 |
$1,504 | 201 | $7,020 | - | - | - | - | - | $1,504 201 MMBtu |
$7,020 - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Natural Gas | Personnel Changes | Administrative Changes | Increase in Production | Natural Gas | Personnel Changes | Administrative Changes | Increase in Production |