IAC Assessment: LS2001
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LS2001
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana State University
Assessment Year 2020
Principal Product Wastewater/Sewage Treatment
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales <$500,000
# of Employees 21
Plant Area (Sq.Ft.) 780,000
Annual Production 5,475,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $563,344 9,996,000 kWh $0.06
Electricity Demand $98,880 24,000 kW-months/year $4.12
Natural Gas $44,864 7,187 MMBtu $6.24
TOTAL ENERGY COSTS $707,088
RECOMMENDED SAVINGS* $205,464 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,297
Cost:
$6
$1,297 23,020 - - $1,297
23,020
kWh
-
-
kW-months/year
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$25,814
Cost:
$6,317
$23,373 414,736 $2,441 593 $23,373
414,736
kWh
$2,441
593
kW-months/year
03: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$1,753
Cost:
$500
$1,753 31,098 - - $1,753
31,098
kWh
-
-
kW-months/year
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$458
Cost:
$158
$458 8,130 - - $458
8,130
kWh
-
-
kW-months/year
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$89,345
Cost:
$41,575
$81,212 1,441,020 $8,133 1,974 $81,212
1,441,020
kWh
$8,133
1,974
kW-months/year
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$86,774
Cost:
$49,800
$86,774 1,539,727 - - $86,774
1,539,727
kWh
-
-
kW-months/year
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$23
Cost:
$25
$23 400 - - $23
400
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$205,464
Cost:
$98,381
$194,890 3,458,131 $10,574 2,567 $194,890
3,458,131
kWh
$10,574
2,567
kW-months/year
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand