IAC Assessment: LS2006
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LS2006
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana State University
Assessment Year 2020
Principal Product Plastics
NAICS 326199 - All Other Plastics Product Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $1,000,000-$5,000,000
# of Employees 14
Plant Area (Sq.Ft.) 19,000
Annual Production 5,000,000 Pieces
Production Hrs. Annual 6,240
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $107,569 1,128,320 kWh $0.10
TOTAL ENERGY COSTS $107,569
RECOMMENDED SAVINGS* $24,393 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,072
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$796
Cost:
$300
$796 8,354 $796
8,354
kWh
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,970
Cost:
$1,800
$5,970 62,625 $5,970
62,625
kWh
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,740
Cost:
-
$5,740 60,205 $5,740
60,205
kWh
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$566
Cost:
$375
$566 5,942 $566
5,942
kWh
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$31
Cost:
$45
$31 328 $31
328
kWh
06: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$1,553
Cost:
$7,413
$1,553 16,286 $1,553
16,286
kWh
07: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$9,737
Cost:
$81,000
$9,737 102,132 $9,737
102,132
kWh
TOTAL RECOMMENDED Savings:
$24,393
Cost:
$90,933
$24,393 255,872 $24,393
255,872
kWh
TOTAL IMPLEMENTED Savings:
$13,072
Cost:
$2,475
$13,072 137,126 $13,072
137,126
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage