IAC Assessment: LS2104
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LS2104
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana State University
Assessment Year 2021
Principal Product Ready Mix Concrete
NAICS 327320 - Ready-Mix Concrete Manufacturing
SIC 3273 - Ready-mixed Concrete
Sales $10,000,000-$50,000,000
# of Employees 32
Plant Area (Sq.Ft.) 146,813
Annual Production 120,000 Units
Production Hrs. Annual 4,160
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $6,138 43,543 kWh $0.14
Natural Gas $912 118 MMBtu $7.73
Fuel Oil #1 $234,750 94,719 MMBtu $2.48
TOTAL ENERGY COSTS $241,800
RECOMMENDED SAVINGS* $15,463 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,597
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #1 Personnel Changes Electricity Usage Fuel Oil #1 Personnel Changes
$ kWh $ MMBtu $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,266
Cost:
$180
$1,266 8,977 - - - - $1,266
8,977
kWh
-
-
MMBtu
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$110
Cost:
$25
$110 777 - - - - $110
777
kWh
-
-
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$993
Cost:
$380
$993 7,044 - - - - $993
7,044
kWh
-
-
MMBtu
-
-
$
04: 2.8226 INCREASE EFFICIENCY OF TRUCKS Savings:
$12,848
Cost:
$5,150
- - $173 70 $12,675 - -
-
kWh
$173
70
MMBtu
$12,675
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$18
Cost:
$23
$18 131 - - - - $18
131
kWh
-
-
MMBtu
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$228
Cost:
$300
$228 1,614 - - - - $228
1,614
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$15,463
Cost:
$6,058
$2,615 18,543 $173 70 $12,675 - $2,615
18,543
kWh
$173
70
MMBtu
$12,675
-
$
TOTAL IMPLEMENTED Savings:
$2,597
Cost:
$885
$2,597 18,412 - - - - $2,597
18,412
kWh
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Fuel Oil #1 Personnel Changes Electricity Usage Fuel Oil #1 Personnel Changes