IAC logo
IAC Assessment: LS2310
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: LS2310
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Louisiana State University
Assessment Year 2023
Principal Product Animal Food
NAICS 311119 - Other Animal Food Manufacturing
SIC 2048 - Prepared Feeds, Nec
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 300,000
Annual Production 5,000,000,000 Units
Production Hrs. Annual 8,736
Location (State) LA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $85,541 722,274 kWh $0.12
Electricity Demand $10,500 2,450 kW-months/year $4.29
LPG $10,000 1,150 MMBtu $8.70
TOTAL ENERGY COSTS $107,421
RECOMMENDED SAVINGS* $82,705 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $47,719
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product
$ kWh $ kW-months/year $ lb $ $ $ $ $ $
01: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$1,380
Cost:
-
- - - - $1,380 180 - - - - - - -
-
kWh
-
-
kW-months/year
$1,380
180
lb
-
-
$
-
-
$
-
-
$
02: 4.661 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT Savings:
$30,000
Cost:
-
- - - - - - - - - - $30,000 - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
$30,000
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,479
Cost:
$275
$3,479 29,479 - - - - - - - - - - $3,479
29,479
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$369
Cost:
$45
$369 3,124 - - - - - - - - - - $369
3,124
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,110
Cost:
$3,822
$9,587 81,242 $523 122 - - - - - - - - $9,587
81,242
kWh
$523
122
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
06: 3.2176 INCREASE USE OF AUTOMATION Savings:
$22,704
Cost:
$21,000
- - - - - - $22,704 - - - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$22,704
-
$
-
-
$
-
-
$
07: 2.7131 ADD AREA LIGHTING SWITCHES Savings:
$127
Cost:
$200
$127 1,077 - - - - - - - - - - $127
1,077
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
08: 4.811 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS Savings:
$14,536
Cost:
$104,400
- - - - - - - - $14,536 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
$14,536
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$82,705
Cost:
$129,742
$13,562 114,922 $523 122 $1,380 180 $22,704 - $14,536 - $30,000 - $13,562
114,922
kWh
$523
122
kW-months/year
$1,380
180
lb
$22,704
-
$
$14,536
-
$
$30,000
-
$
TOTAL IMPLEMENTED Savings:
$47,719
Cost:
$129,267
$9,956 84,366 $523 122 - - $22,704 - $14,536 - - - $9,956
84,366
kWh
$523
122
kW-months/year
-
-
lb
$22,704
-
$
$14,536
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $ $ $ $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product Electricity Usage Electricity Demand Solid Waste (non-haz) Personnel Changes Administrative Changes Primary Product