Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana Tech |
---|---|
Assessment Year | 2022 |
Principal Product | paper processing fabrics |
NAICS | 332618 - Other Fabricated Wire Product Manufacturing |
SIC | 3496 - Misc. Fabricated Wire Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 128,000 |
Annual Production | 70,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $441,233 | 4,085,496 | kWh | $0.11 |
Electricity Demand | $124,969 | 11,148 | kW-months/year | $11.21 |
LPG | $713 | 22 | MMBtu | $32.60 |
TOTAL ENERGY COSTS | $567,665 | |||
RECOMMENDED SAVINGS* | $42,303 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $673 Cost: - |
- | - | - | - | $673 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$673 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $21,493 Cost: $30,000 |
$21,493 | 199,009 | - | - | - | - | - | - | - | - | - | - |
$21,493 199,009 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,079 Cost: - |
$5,079 | 47,050 | - | - | - | - | - | - | - | - | - | - |
$5,079 47,050 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $808 Cost: $29,000 |
$(-59) | (-549) | - | - | - | - | $712 | 23 | - | - | $155 | - |
$(-59) (-549) kWh |
- - kW-months/year |
- - $ |
$712 23 MMBtu |
- - $ |
$155 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $10,089 Cost: - |
- | - | $10,089 | 900 | - | - | - | - | - | - | - | - |
- - kWh |
$10,089 900 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $3,938 Cost: - |
$4,118 | 38,126 | - | - | - | - | - | - | $(-180) | - | - | - |
$4,118 38,126 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$(-180) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $223 Cost: $180 |
$403 | 3,734 | - | - | - | - | - | - | $(-180) | - | - | - |
$403 3,734 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$(-180) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,303 Cost: $59,180 |
$31,033 | 287,370 | $10,089 | 900 | $673 | - | $712 | 23 | $(-360) | - | $155 | - | $31,033 287,370 kWh |
$10,089 900 kW-months/year |
$673 - $ |
$712 23 MMBtu |
$(-360) - $ |
$155 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Personnel Changes | Ancillary Material Cost |