Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana Tech |
---|---|
Assessment Year | 2023 |
Principal Product | Work Orders |
NAICS | 336510 - Railroad Rolling Stock Manufacturing |
SIC | 3999 - Manufacturing Industries, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 138 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 750 Units |
Production Hrs. Annual | 2,496 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $89,811 | 1,080,594 | kWh | $0.08 |
Electricity Demand | $79,502 | 5,521 | kW-months/year | $14.40 |
TOTAL ENERGY COSTS | $171,679 | |||
RECOMMENDED SAVINGS* | $23,701 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $2,583 Cost: $2,922 |
$1,780 | 21,416 | $865 | 60 | $(-62) | - |
$1,780 21,416 kWh |
$865 60 kW-months/year |
$(-62) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $916 Cost: $843 |
$706 | 8,498 | $210 | 15 | - | - |
$706 8,498 kWh |
$210 15 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,502 Cost: $255 |
$2,502 | 30,105 | - | - | - | - |
$2,502 30,105 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $17,700 Cost: $1,500 |
- | - | - | - | $17,700 | - |
- - kWh |
- - kW-months/year |
$17,700 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,701 Cost: $5,520 |
$4,988 | 60,019 | $1,075 | 75 | $17,638 | - | $4,988 60,019 kWh |
$1,075 75 kW-months/year |
$17,638 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost |