IAC Assessment: MA0130
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0130
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1988
Principal Product FORMED SHEET METAL PARTS
NAICS n/a
SIC 3444 - Sheet Metalwork
Sales $1,000,000-$5,000,000
# of Employees 52
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 2,470
Location (State) CT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $36,997 419,402 kWh $0.09
Natural Gas $8,319 1,190 MMBtu $6.99
TOTAL ENERGY COSTS $45,316
RECOMMENDED SAVINGS* $4,283 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$154
Cost:
$126
$154 1,758 - - $154
1,758
kWh
-
-
MMBtu
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$937
Cost:
$139
- - $937 134 -
-
kWh
$937
134
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$753
Cost:
$1,672
$753 8,499 - - $753
8,499
kWh
-
-
MMBtu
04: 2.6232 INSTALL SET-BACK TIMERS Savings:
$224
Cost:
$225
$224 2,638 - - $224
2,638
kWh
-
-
MMBtu
05: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$2,215
Cost:
$5,400
$2,215 25,205 - - $2,215
25,205
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$4,283
Cost:
$7,562
$3,346 38,100 $937 134 $3,346
38,100
kWh
$937
134
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas