IAC Assessment: MA0159
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0159
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1989
Principal Product CUSTOM URETHANE PRODUCTS
NAICS n/a
SIC 3061 - Mechanical Rubber Goods
Sales $10,000,000-$50,000,000
# of Employees 290
Plant Area (Sq.Ft.) 0
Annual Production 1,800,000 Pounds
Production Hrs. Annual 7,200
Location (State) NH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $546,575 8,135,111 kWh $0.07
LPG $72,234 14,748 MMBtu $4.90
Fuel Oil #4 $91,060 25,344 MMBtu $3.59
TOTAL ENERGY COSTS $709,869
RECOMMENDED SAVINGS* $16,510 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,178
#|Description Savings
Cost
Status Electricity Usage LPG Fuel Oil #4 Administrative Changes Electricity Usage LPG Fuel Oil #4 Administrative Changes
$ kWh $ MMBtu $ MMBtu $ $
01: 2.2532 USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD Savings:
$10,055
Cost:
$12,760
$4,253 63,306 $5,802 1,189 - - - - $4,253
63,306
kWh
$5,802
1,189
MMBtu
-
-
MMBtu
-
-
$
02: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR Savings:
$684
Cost:
$3,027
- - - - $684 191 - - -
-
kWh
-
-
MMBtu
$684
191
MMBtu
-
-
$
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$2,298
Cost:
$2,700
- - - - $2,298 642 - - -
-
kWh
-
-
MMBtu
$2,298
642
MMBtu
-
-
$
04: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$444
Cost:
$297
- - - - $444 124 - - -
-
kWh
-
-
MMBtu
$444
124
MMBtu
-
-
$
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$980
Cost:
$1,800
- - - - - - $980 - -
-
kWh
-
-
MMBtu
-
-
MMBtu
$980
-
$
06: 2.2532 USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD Savings:
$752
Cost:
-
$127 1,758 $625 128 - - - - $127
1,758
kWh
$625
128
MMBtu
-
-
MMBtu
-
-
$
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,297
Cost:
$2,190
$1,805 26,964 $(-508) (-104) - - - - $1,805
26,964
kWh
$(-508)
(-104)
MMBtu
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$16,510
Cost:
$22,774
$6,185 92,028 $5,919 1,213 $3,426 957 $980 - $6,185
92,028
kWh
$5,919
1,213
MMBtu
$3,426
957
MMBtu
$980
-
$
TOTAL IMPLEMENTED Savings:
$4,178
Cost:
$6,024
$127 1,758 $625 128 $3,426 957 - - $127
1,758
kWh
$625
128
MMBtu
$3,426
957
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ $
Electricity Usage LPG Fuel Oil #4 Administrative Changes Electricity Usage LPG Fuel Oil #4 Administrative Changes