Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1989 |
Principal Product | AUTOMOTIVE BATTERIES |
NAICS | n/a |
SIC | 3692 - Primary Batteries, Dry And Wet |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,500,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | VT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,124,597 | 15,167,058 | kWh | $0.07 |
LPG | $258,237 | 58,074 | MMBtu | $4.45 |
Fuel Oil #2 | $22,400 | 22,400 | MMBtu | $1.00 |
TOTAL ENERGY COSTS | $1,405,234 | |||
RECOMMENDED SAVINGS* | $52,647 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,130 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Fuel Oil #2 | Electricity Usage | LPG | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8223 ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE |
Savings: $19,320 Cost: $18,000 |
- | - | - | - | $19,320 | 2,705 |
- - kWh |
- - MMBtu |
$19,320 2,705 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $3,628 Cost: $3,450 |
$4,780 | 64,478 | $(-1,152) | (-259) | - | - |
$4,780 64,478 kWh |
$(-1,152) (-259) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,130 Cost: $180 |
$1,130 | 15,240 | - | - | - | - |
$1,130 15,240 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $842 Cost: $1,700 |
$842 | 13,189 | - | - | - | - |
$842 13,189 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $21,230 Cost: $7,913 |
$27,967 | 377,198 | $(-6,737) | (-1,514) | - | - |
$27,967 377,198 kWh |
$(-6,737) (-1,514) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,497 Cost: $908 |
$6,497 | 87,632 | - | - | - | - |
$6,497 87,632 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $52,647 Cost: $32,151 |
$41,216 | 557,737 | $(-7,889) | (-1,773) | $19,320 | 2,705 | $41,216 557,737 kWh |
$(-7,889) (-1,773) MMBtu |
$19,320 2,705 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,130 Cost: $180 |
$1,130 | 15,240 | - | - | - | - | $1,130 15,240 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Fuel Oil #2 | Electricity Usage | LPG | Fuel Oil #2 |