Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1990 |
Principal Product | DISPOSABLE MED. PRODUCTS |
NAICS | n/a |
SIC | 3842 - Surgical Appliances And Supplies |
Sales | $10,000,000-$50,000,000 |
# of Employees | 74 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 7,500,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $56,244 | 519,050 | kWh | $0.11 |
Other Energy | $34,170 | 4,880 | MMBtu | $7.00 |
TOTAL ENERGY COSTS | $90,414 | |||
RECOMMENDED SAVINGS* | $8,035 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,035 |
#|Description |
Savings Cost |
Status | Electricity Usage | Other Energy | Electricity Usage | Other Energy | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $434 Cost: - |
$434 | 4,103 | - | - |
$434 4,103 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $296 Cost: $93 |
$296 | 2,638 | - | - |
$296 2,638 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7421 REDUCE GLAZED AREAS IN BUILDINGS |
Savings: $2,169 Cost: $13,560 |
- | - | $2,169 | 310 |
- - kWh |
$2,169 310 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $985 Cost: $100 |
$985 | 9,086 | - | - |
$985 9,086 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7493 USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES |
Savings: $4,151 Cost: $99,400 |
- | - | $4,151 | 593 |
- - kWh |
$4,151 593 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,035 Cost: $113,153 |
$1,715 | 15,827 | $6,320 | 903 | $1,715 15,827 kWh |
$6,320 903 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,035 Cost: $113,153 |
$1,715 | 15,827 | $6,320 | 903 | $1,715 15,827 kWh |
$6,320 903 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Other Energy | Electricity Usage | Other Energy |