Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1992 |
Principal Product | HEAVY MACHINERY |
NAICS | n/a |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 4,290 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $226,535 | 2,235,053 | kWh | $0.10 |
Natural Gas | $77,754 | 14,889 | MMBtu | $5.22 |
Fuel Oil #6 | $53,544 | 15,034 | MMBtu | $3.56 |
TOTAL ENERGY COSTS | $357,833 | |||
RECOMMENDED SAVINGS* | $48,197 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,134 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Fuel Oil #6 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Fuel Oil #6 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $12,894 Cost: $33 |
$12,894 | 127,198 | - | - | - | - | - | - | - | - |
$12,894 127,198 kWh |
- - MMBtu |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6124 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE |
Savings: $11,199 Cost: $1,500 |
- | - | $6,265 | 1,276 | - | - | $4,934 | 1,386 | - | - |
- - kWh |
$6,265 1,276 MMBtu |
- - MMBtu |
$4,934 1,386 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $12,146 Cost: $200 |
- | - | $6,795 | 1,384 | - | - | $5,351 | 1,503 | - | - |
- - kWh |
$6,795 1,384 MMBtu |
- - MMBtu |
$5,351 1,503 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7423 REDUCE HEAT GAIN BY WINDOW TINTING |
Savings: $5,744 Cost: $5,800 |
- | - | - | - | $3,159 | 523 | $2,585 | 330 | - | - |
- - kWh |
- - MMBtu |
$3,159 523 MMBtu |
$2,585 330 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $3,319 Cost: - |
$3,981 | 39,273 | - | - | - | - | $(-662) | (-186) | - | - |
$3,981 39,273 kWh |
- - MMBtu |
- - MMBtu |
$(-662) (-186) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $980 Cost: $4 |
$980 | 9,672 | - | - | - | - | - | - | - | - |
$980 9,672 kWh |
- - MMBtu |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $785 Cost: $1 |
- | - | $776 | 158 | - | - | $609 | 171 | $(-600) | - |
- - kWh |
$776 158 MMBtu |
- - MMBtu |
$609 171 MMBtu |
$(-600) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $365 Cost: $220 |
- | - | $205 | 42 | - | - | $160 | 45 | - | - |
- - kWh |
$205 42 MMBtu |
- - MMBtu |
$160 45 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $468 Cost: $180 |
$468 | 4,689 | - | - | - | - | - | - | - | - |
$468 4,689 kWh |
- - MMBtu |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $297 Cost: $400 |
$297 | 2,931 | - | - | - | - | - | - | - | - |
$297 2,931 kWh |
- - MMBtu |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,197 Cost: $8,338 |
$18,620 | 183,763 | $14,041 | 2,860 | $3,159 | 523 | $12,977 | 3,249 | $(-600) | - | $18,620 183,763 kWh |
$14,041 2,860 MMBtu |
$3,159 523 MMBtu |
$12,977 3,249 MMBtu |
$(-600) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,134 Cost: $2,538 |
$14,639 | 144,490 | $14,041 | 2,860 | - | - | $11,054 | 3,105 | $(-600) | - | $14,639 144,490 kWh |
$14,041 2,860 MMBtu |
- - MMBtu |
$11,054 3,105 MMBtu |
$(-600) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Fuel Oil #6 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Fuel Oil #6 | Administrative Changes |