IAC Assessment: MA0248
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0248
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1992
Principal Product FROZEN CHICKEN ENTREES
NAICS n/a
SIC 2015 - Poultry Slaughtering And Processing
Sales $10,000,000-$50,000,000
# of Employees 352
Plant Area (Sq.Ft.) 0
Annual Production 26,000,000 Pounds
Production Hrs. Annual 6,240
Location (State) ME
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $363,785 3,978,898 kWh $0.09
Natural Gas $56,015 9,663 MMBtu $5.80
TOTAL ENERGY COSTS $419,800
RECOMMENDED SAVINGS* $25,298 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,673
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$13,681
Cost:
$30,404
$(-616) (-6,741) $14,297 2,465 $(-616)
(-6,741)
kWh
$14,297
2,465
MMBtu
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$3,051
Cost:
$10
- - $3,051 526 -
-
kWh
$3,051
526
MMBtu
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$2,622
Cost:
$1,872
- - $2,622 452 -
-
kWh
$2,622
452
MMBtu
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,618
Cost:
$(-2,762)
$3,618 39,566 - - $3,618
39,566
kWh
-
-
MMBtu
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,229
Cost:
$7,164
$1,229 13,482 - - $1,229
13,482
kWh
-
-
MMBtu
06: 2.6232 INSTALL SET-BACK TIMERS Savings:
$268
Cost:
$150
$268 2,931 - - $268
2,931
kWh
-
-
MMBtu
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$829
Cost:
-
$829 9,086 - - $829
9,086
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$25,298
Cost:
$36,838
$5,328 58,324 $19,970 3,443 $5,328
58,324
kWh
$19,970
3,443
MMBtu
TOTAL IMPLEMENTED Savings:
$5,673
Cost:
$1,882
- - $5,673 978 -
-
kWh
$5,673
978
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas