Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1994 |
Principal Product | Broach cutting tools |
NAICS | n/a |
SIC | 3541 - Machine Tools, Metal Cutting Types |
Sales | $5,000,000-$10,000,000 |
# of Employees | 36 |
Plant Area (Sq.Ft.) | 18,000 |
Annual Production | 1,050 Pieces |
Production Hrs. Annual | 5,928 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $99,324 | 710,727 | kWh | $0.14 |
Natural Gas | $4,511 | 623 | MMBtu | $7.24 |
TOTAL ENERGY COSTS | $103,835 | |||
RECOMMENDED SAVINGS* | $4,395 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,043 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,966 Cost: $50 |
$1,966 | 14,068 | - | - |
$1,966 14,068 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,024 Cost: $62 |
$1,024 | 7,327 | - | - |
$1,024 7,327 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $1,077 Cost: $475 |
- | - | $1,077 | 149 |
- - kWh |
$1,077 149 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $205 Cost: - |
$205 | 1,465 | - | - |
$205 1,465 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $123 Cost: $109 |
$123 | 879 | - | - |
$123 879 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $4,395 Cost: $696 |
$3,318 | 23,739 | $1,077 | 149 | $3,318 23,739 kWh |
$1,077 149 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,043 Cost: $525 |
$1,966 | 14,068 | $1,077 | 149 | $1,966 14,068 kWh |
$1,077 149 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |