IAC Assessment: MA0366
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0366
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1996
Principal Product solar panel technology and equipment
NAICS n/a
SIC 3674 - Semiconductors And Related Devices
Sales $10,000,000-$50,000,000
# of Employees 140
Plant Area (Sq.Ft.) 72,000
Annual Production 2,000 Pieces
Production Hrs. Annual 6,000
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $600,876 6,534,291 kWh $0.09
Electricity Demand $148,923 10,901 kW-months/year $13.66
Electricity Fees $22,737 - $ -
Natural Gas $56,522 3,750 MMBtu $15.07
TOTAL ENERGY COSTS $829,058
RECOMMENDED SAVINGS* $56,242 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,843
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,638
Cost:
-
- - - - - - $1,638 315 - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,638
315
MMBtu
-
-
Tgal
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$11,369
Cost:
$9,450
- - - - $11,369 - - - - - -
-
kWh
-
-
kW-months/year
$11,369
-
$
-
-
MMBtu
-
-
Tgal
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$31,893
Cost:
$20,255
$30,986 366,354 $907 75 - - - - - - $30,986
366,354
kWh
$907
75
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
04: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING Savings:
$5,919
Cost:
$9,000
$5,919 91,735 - - - - - - - - $5,919
91,735
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,474
Cost:
$350
$1,309 8,206 $165 17 - - - - - - $1,309
8,206
kWh
$165
17
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
06: 3.4115 RECOVER AND REUSE COOLING WATER Savings:
$1,421
Cost:
$1,471
- - - - - - - - $1,421 131,250 -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$1,421
131,250
Tgal
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,093
Cost:
$4,910
$2,093 35,756 - - - - - - - - $2,093
35,756
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
08: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD Savings:
$435
Cost:
$250
$435 6,741 - - - - - - - - $435
6,741
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
TOTAL RECOMMENDED Savings:
$56,242
Cost:
$45,686
$40,742 508,792 $1,072 92 $11,369 - $1,638 315 $1,421 131,250 $40,742
508,792
kWh
$1,072
92
kW-months/year
$11,369
-
$
$1,638
315
MMBtu
$1,421
131,250
Tgal
TOTAL IMPLEMENTED Savings:
$12,843
Cost:
$9,800
$1,309 8,206 $165 17 $11,369 - - - - - $1,309
8,206
kWh
$165
17
kW-months/year
$11,369
-
$
-
-
MMBtu
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal
Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal