Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1997 |
Principal Product | Electro-Magnetic Coil Windings |
NAICS | n/a |
SIC | 3677 - Electronic Coils And Transformers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 29,000 |
Annual Production | 5,000,000 Pieces |
Production Hrs. Annual | 6,500 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $123,215 | 1,302,462 | kWh | $0.09 |
Electricity Demand | $40,052 | 4,198 | kW-months/year | $9.54 |
Natural Gas | $9,762 | 1,111 | MMBtu | $8.79 |
TOTAL ENERGY COSTS | $185,261 | |||
RECOMMENDED SAVINGS* | $106,252 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $106,252 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $92,750 Cost: $68,000 |
- | - | - | - | - | - | $92,750 | - |
- - kWh |
- - kW-months/year |
- - lb |
$92,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $8,750 Cost: $1,000 |
- | - | - | - | - | - | $8,750 | - |
- - kWh |
- - kW-months/year |
- - lb |
$8,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,550 Cost: $356 |
$2,550 | 43,669 | - | - | - | - | - | - |
$2,550 43,669 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $1,895 Cost: $10 |
$1,654 | 28,429 | $241 | 48 | - | - | - | - |
$1,654 28,429 kWh |
$241 48 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $160 Cost: - |
- | - | - | - | $160 | 2,073,600 | - | - |
- - kWh |
- - kW-months/year |
$160 2,073,600 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $147 Cost: - |
$147 | 2,345 | - | - | - | - | - | - |
$147 2,345 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $106,252 Cost: $69,366 |
$4,351 | 74,443 | $241 | 48 | $160 | 2,073,600 | $101,500 | - | $4,351 74,443 kWh |
$241 48 kW-months/year |
$160 2,073,600 lb |
$101,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $106,252 Cost: $69,366 |
$4,351 | 74,443 | $241 | 48 | $160 | 2,073,600 | $101,500 | - | $4,351 74,443 kWh |
$241 48 kW-months/year |
$160 2,073,600 lb |
$101,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Primary Raw Material |