Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 1997 |
Principal Product | dining furniture |
NAICS | n/a |
SIC | 2512 - Upholstered Household Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 105,000 |
Annual Production | 15,000 Thousand Feet |
Production Hrs. Annual | 2,250 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $114,079 | 1,131,887 | kWh | $0.10 |
Electricity Demand | $47,187 | 4,776 | kW-months/year | $9.88 |
LPG | $505 | 17 | MMBtu | $29.71 |
Fuel Oil #2 | $15,097 | 3,046 | MMBtu | $4.96 |
TOTAL ENERGY COSTS | $185,502 | |||
RECOMMENDED SAVINGS* | $12,267 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,061 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $8,941 Cost: $16,900 |
$(-202) | (-2,931) | - | - | - | - | $9,143 | - | - | - | - | - |
$(-202) (-2,931) kWh |
- - MMBtu |
- - lb |
$9,143 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL |
Savings: $440 Cost: - |
- | - | $440 | 89 | - | - | - | - | - | - | - | - |
- - kWh |
$440 89 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $20 Cost: - |
- | - | - | - | $1,270 | 72,000 | $(-1,250) | - | - | - | - | - |
- - kWh |
- - MMBtu |
$1,270 72,000 lb |
$(-1,250) - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $1,153 Cost: - |
- | - | - | - | - | - | - | - | $1,153 | - | - | - |
- - kWh |
- - MMBtu |
- - lb |
- - $ |
$1,153 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $888 Cost: $992 |
$888 | 12,896 | - | - | - | - | - | - | - | - | - | - |
$888 12,896 kWh |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4145 USE MAGNETIC TECHNOLOGY TO TREAT WATER |
Savings: $825 Cost: $5,200 |
- | - | - | - | - | - | - | - | - | - | $825 | - |
- - kWh |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$825 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,267 Cost: $23,092 |
$686 | 9,965 | $440 | 89 | $1,270 | 72,000 | $7,893 | - | $1,153 | - | $825 | - | $686 9,965 kWh |
$440 89 MMBtu |
$1,270 72,000 lb |
$7,893 - $ |
$1,153 - $ |
$825 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,061 Cost: $992 |
$888 | 12,896 | - | - | $1,270 | 72,000 | $(-1,250) | - | $1,153 | - | - | - | $888 12,896 kWh |
- - MMBtu |
$1,270 72,000 lb |
$(-1,250) - $ |
$1,153 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |