IAC logo
IAC Assessment: MA0398
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0398
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 1997
Principal Product Specialized Industrial Machinery, NFC
NAICS n/a
SIC 3559 - Special Industry Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 70
Plant Area (Sq.Ft.) 26,000
Annual Production 0 Units
Production Hrs. Annual 4,810
Location (State) RI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $41,424 505,569 kWh $0.08
Electricity Demand $15,238 2,881 kW-months/year $5.29
Natural Gas $25,931 2,955 MMBtu $8.78
TOTAL ENERGY COSTS $82,593
RECOMMENDED SAVINGS* $11,720 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,863
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Water Consumption Electricity Usage Electricity Demand Administrative Changes Water Consumption
$ kWh $ kW-months/year $ $ $ Tgal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,098
Cost:
$34,200
$5,146 73,857 $952 180 - - - - $5,146
73,857
kWh
$952
180
kW-months/year
-
-
$
-
-
Tgal
02: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$2,759
Cost:
$10,560
$(-169) (-1,758) - - - - $2,928 - $(-169)
(-1,758)
kWh
-
-
kW-months/year
-
-
$
$2,928
-
Tgal
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,450
Cost:
$384
$1,450 20,809 - - - - - - $1,450
20,809
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
04: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$1,067
Cost:
-
- - - - $1,067 - - - -
-
kWh
-
-
kW-months/year
$1,067
-
$
-
-
Tgal
05: 4.8210 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$346
Cost:
-
- - - - $346 - - - -
-
kWh
-
-
kW-months/year
$346
-
$
-
-
Tgal
TOTAL RECOMMENDED Savings:
$11,720
Cost:
$45,144
$6,427 92,908 $952 180 $1,413 - $2,928 - $6,427
92,908
kWh
$952
180
kW-months/year
$1,413
-
$
$2,928
-
Tgal
TOTAL IMPLEMENTED Savings:
$2,863
Cost:
$384
$1,450 20,809 - - $1,413 - - - $1,450
20,809
kWh
-
-
kW-months/year
$1,413
-
$
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ Tgal
Electricity Usage Electricity Demand Administrative Changes Water Consumption Electricity Usage Electricity Demand Administrative Changes Water Consumption