Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2004 |
Principal Product | Automotive components |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 267 |
Plant Area (Sq.Ft.) | 360,000 |
Annual Production | 6,000,000 Pieces |
Production Hrs. Annual | 6,144 |
Location (State) | NH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,016,591 | 19,373,978 | kWh | $0.05 |
Electricity Demand | $180,052 | 28,507 | kW-months/year | $6.32 |
Natural Gas | $583,933 | 60,486 | MMBtu | $9.65 |
LPG | $94,585 | 11,984 | MMBtu | $7.89 |
TOTAL ENERGY COSTS | $1,903,865 | |||
RECOMMENDED SAVINGS* | $243,653 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $243,653 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | LPG | Electricity Usage | Electricity Demand | Natural Gas | LPG | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $212,625 Cost: $986,100 |
$192,593 | 2,663,800 | $20,032 | 2,622 | - | - | - | - |
$192,593 2,663,800 kWh |
$20,032 2,622 kW-months/year |
- - MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $16,690 Cost: $81,637 |
$34,950 | 483,400 | $1,933 | 253 | $(-20,193) | (-2,050) | - | - |
$34,950 483,400 kWh |
$1,933 253 kW-months/year |
$(-20,193) (-2,050) MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY |
Savings: $1,915 Cost: $44,790 |
$795 | 11,000 | - | - | $1,120 | 1,142 | - | - |
$795 11,000 kWh |
- - kW-months/year |
$1,120 1,142 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,282 Cost: $5,430 |
$3,282 | 45,400 | - | - | - | - | - | - |
$3,282 45,400 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,840 Cost: $500 |
- | - | - | - | - | - | $2,840 | 360 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,840 360 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,791 Cost: $4,850 |
$2,791 | 38,600 | - | - | - | - | - | - |
$2,791 38,600 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,836 Cost: $768 |
$1,836 | 25,400 | - | - | - | - | - | - |
$1,836 25,400 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,139 Cost: $650 |
- | - | - | - | $1,139 | 118 | - | - |
- - kWh |
- - kW-months/year |
$1,139 118 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $535 Cost: $180 |
$535 | 7,400 | - | - | - | - | - | - |
$535 7,400 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $243,653 Cost: $1,124,905 |
$236,782 | 3,275,000 | $21,965 | 2,875 | $(-17,934) | (-790) | $2,840 | 360 | $236,782 3,275,000 kWh |
$21,965 2,875 kW-months/year |
$(-17,934) (-790) MMBtu |
$2,840 360 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $243,653 Cost: $1,124,905 |
$236,782 | 3,275,000 | $21,965 | 2,875 | $(-17,934) | (-790) | $2,840 | 360 | $236,782 3,275,000 kWh |
$21,965 2,875 kW-months/year |
$(-17,934) (-790) MMBtu |
$2,840 360 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | LPG | Electricity Usage | Electricity Demand | Natural Gas | LPG |