Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2008 |
Principal Product | fine paper |
NAICS | 322121 - Paper (except Newsprint) Mills |
SIC | 2621 - Paper Mills |
Sales | $50,000,000-$100,000,000 |
# of Employees | 48 |
Plant Area (Sq.Ft.) | 160,000 |
Annual Production | 10,950 Tons |
Production Hrs. Annual | 8,520 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $829,451 | 10,061,141 | kWh | $0.08 |
Electricity Demand | $335,304 | 23,238 | kW-months/year | $14.43 |
Electricity Fees | $120,528 | - | $ | - |
Natural Gas | $1,320,657 | 122,732 | MMBtu | $10.76 |
TOTAL ENERGY COSTS | $2,605,940 | |||
RECOMMENDED SAVINGS* | $501,375 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $115,058 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $221,387 Cost: $110,000 |
- | - | - | - | $221,387 | 20,575 |
- - kWh |
- - kW-months/year |
$221,387 20,575 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $147,853 Cost: $540,000 |
$(-15,712) | (-190,678) | $(-3,882) | (-269) | $167,447 | 15,562 |
$(-15,712) (-190,678) kWh |
$(-3,882) (-269) kW-months/year |
$167,447 15,562 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3322 USE EXISTING DAM TO GENERATE ELECTRICITY |
Savings: $110,112 Cost: $939,500 |
$88,827 | 1,078,000 | $21,285 | 1,482 | - | - |
$88,827 1,078,000 kWh |
$21,285 1,482 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,946 Cost: $18,000 |
$3,964 | 48,104 | $982 | 68 | - | - |
$3,964 48,104 kWh |
$982 68 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3321 USE STEAM PRESSURE REDUCTION TO GENERATE POWER |
Savings: $8,663 Cost: $5,000 |
$16,849 | 204,480 | $4,156 | 288 | $(-12,342) | (-1,147) |
$16,849 204,480 kWh |
$4,156 288 kW-months/year |
$(-12,342) (-1,147) MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,272 Cost: - |
$4,272 | 51,845 | - | - | - | - |
$4,272 51,845 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,142 Cost: $20,000 |
$4,142 | 50,268 | - | - | - | - |
$4,142 50,268 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $501,375 Cost: $1,632,500 |
$102,342 | 1,242,019 | $22,541 | 1,569 | $376,492 | 34,990 | $102,342 1,242,019 kWh |
$22,541 1,569 kW-months/year |
$376,492 34,990 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $115,058 Cost: $957,500 |
$92,791 | 1,126,104 | $22,267 | 1,550 | - | - | $92,791 1,126,104 kWh |
$22,267 1,550 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |