IAC Assessment: MA0636
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0636
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2008
Principal Product fine paper
NAICS 322121 - Paper (except Newsprint) Mills
SIC 2621 - Paper Mills
Sales $50,000,000-$100,000,000
# of Employees 48
Plant Area (Sq.Ft.) 160,000
Annual Production 10,950 Tons
Production Hrs. Annual 8,520
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $829,451 10,061,141 kWh $0.08
Electricity Demand $335,304 23,238 kW-months/year $14.43
Electricity Fees $120,528 - $ -
Natural Gas $1,320,657 122,732 MMBtu $10.76
TOTAL ENERGY COSTS $2,605,940
RECOMMENDED SAVINGS* $501,375 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $115,058
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$221,387
Cost:
$110,000
- - - - $221,387 20,575 -
-
kWh
-
-
kW-months/year
$221,387
20,575
MMBtu
02: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS Savings:
$147,853
Cost:
$540,000
$(-15,712) (-190,678) $(-3,882) (-269) $167,447 15,562 $(-15,712)
(-190,678)
kWh
$(-3,882)
(-269)
kW-months/year
$167,447
15,562
MMBtu
03: 2.3322 USE EXISTING DAM TO GENERATE ELECTRICITY Savings:
$110,112
Cost:
$939,500
$88,827 1,078,000 $21,285 1,482 - - $88,827
1,078,000
kWh
$21,285
1,482
kW-months/year
-
-
MMBtu
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,946
Cost:
$18,000
$3,964 48,104 $982 68 - - $3,964
48,104
kWh
$982
68
kW-months/year
-
-
MMBtu
05: 2.3321 USE STEAM PRESSURE REDUCTION TO GENERATE POWER Savings:
$8,663
Cost:
$5,000
$16,849 204,480 $4,156 288 $(-12,342) (-1,147) $16,849
204,480
kWh
$4,156
288
kW-months/year
$(-12,342)
(-1,147)
MMBtu
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,272
Cost:
-
$4,272 51,845 - - - - $4,272
51,845
kWh
-
-
kW-months/year
-
-
MMBtu
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,142
Cost:
$20,000
$4,142 50,268 - - - - $4,142
50,268
kWh
-
-
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$501,375
Cost:
$1,632,500
$102,342 1,242,019 $22,541 1,569 $376,492 34,990 $102,342
1,242,019
kWh
$22,541
1,569
kW-months/year
$376,492
34,990
MMBtu
TOTAL IMPLEMENTED Savings:
$115,058
Cost:
$957,500
$92,791 1,126,104 $22,267 1,550 - - $92,791
1,126,104
kWh
$22,267
1,550
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas