Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2012 |
Principal Product | Talc powder |
NAICS | 212393 - Other Chemical and Fertilizer Mineral Mining |
SIC | 3295 - Minerals, Ground Or Treated |
Sales | $1,000,000-$5,000,000 |
# of Employees | 26 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 80,000 Tons |
Production Hrs. Annual | 6,240 |
Location (State) | VT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $397,465 | 4,724,400 | kWh | $0.08 |
Electricity Demand | $269,084 | 19,284 | kW-months/year | $13.95 |
Electricity Fees | $6,722 | - | $ | - |
LPG | $35,920 | 1,513 | MMBtu | $23.74 |
Fuel Oil #2 | $174,807 | 7,312 | MMBtu | $23.91 |
Other Energy | $4,674 | 166 | MMBtu | $28.16 |
TOTAL ENERGY COSTS | $888,672 | |||
RECOMMENDED SAVINGS* | $55,007 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $41,737 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #2 | Ancillary Material Cost | Electricity Usage | Fuel Oil #2 | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $19,393 Cost: $39,000 |
$4,393 | 52,241 | - | - | $15,000 | - |
$4,393 52,241 kWh |
- - MMBtu |
$15,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $15,781 Cost: $2,800 |
$15,781 | 187,649 | - | - | - | - |
$15,781 187,649 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2211 USE OPTIMUM TEMPERATURE |
Savings: $6,647 Cost: $4,000 |
- | - | $6,647 | 278 | - | - |
- - kWh |
$6,647 278 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $3,539 Cost: $17,500 |
- | - | $3,539 | 148 | - | - |
- - kWh |
$3,539 148 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,048 Cost: $6,600 |
$3,048 | 36,242 | - | - | - | - |
$3,048 36,242 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,462 Cost: $6,035 |
$2,462 | 29,283 | - | - | - | - |
$2,462 29,283 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,810 Cost: $200 |
$1,810 | 21,528 | - | - | - | - |
$1,810 21,528 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,705 Cost: $4,080 |
$1,705 | 20,274 | - | - | - | - |
$1,705 20,274 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $622 Cost: $1,100 |
- | - | $622 | 26 | - | - |
- - kWh |
$622 26 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,007 Cost: $81,315 |
$29,199 | 347,217 | $10,808 | 452 | $15,000 | - | $29,199 347,217 kWh |
$10,808 452 MMBtu |
$15,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $41,737 Cost: $52,680 |
$26,737 | 317,934 | - | - | $15,000 | - | $26,737 317,934 kWh |
- - MMBtu |
$15,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #2 | Ancillary Material Cost | Electricity Usage | Fuel Oil #2 | Ancillary Material Cost |