IAC Assessment: MA0729
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0729
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2014
Principal Product printed fabric
NAICS 313310 - Textile and Fabric Finishing Mills
SIC 2261 - Finishing Plants, Cotton
Sales $10,000,000-$50,000,000
# of Employees 80
Plant Area (Sq.Ft.) 246,300
Annual Production 30,000 Thousand Feet
Production Hrs. Annual 4,400
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $467,238 3,853,400 kWh $0.12
Electricity Demand $174,041 16,569 kW-months/year $10.50
Electricity Fees $42,650 - $ -
Natural Gas $900,649 98,936 MMBtu $9.10
Fuel Oil #6 $11,663 669 MMBtu $17.43
TOTAL ENERGY COSTS $1,839,294
RECOMMENDED SAVINGS* $61,073 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,619
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Liquid (non-haz) Electricity Usage Natural Gas Other Liquid (non-haz)
$ kWh $ MMBtu $ gal
01: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$25,718
Cost:
$11,750
- - $8,172 1,091 $17,546 3,377,220 -
-
kWh
$8,172
1,091
MMBtu
$17,546
3,377,220
gal
02: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$14,490
Cost:
$500
$14,490 119,460 - - - - $14,490
119,460
kWh
-
-
MMBtu
-
-
gal
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,956
Cost:
$3,300
$8,956 73,836 - - - - $8,956
73,836
kWh
-
-
MMBtu
-
-
gal
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$8,114
Cost:
$9,050
$8,114 66,896 - - - - $8,114
66,896
kWh
-
-
MMBtu
-
-
gal
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$2,622
Cost:
$2,690
- - $2,622 350 - - -
-
kWh
$2,622
350
MMBtu
-
-
gal
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,173
Cost:
$200
$1,173 9,672 - - - - $1,173
9,672
kWh
-
-
MMBtu
-
-
gal
TOTAL RECOMMENDED Savings:
$61,073
Cost:
$27,490
$32,733 269,864 $10,794 1,441 $17,546 3,377,220 $32,733
269,864
kWh
$10,794
1,441
MMBtu
$17,546
3,377,220
gal
TOTAL IMPLEMENTED Savings:
$24,619
Cost:
$4,000
$24,619 202,968 - - - - $24,619
202,968
kWh
-
-
MMBtu
-
-
gal
Savings
Cost
$ kWh $ MMBtu $ gal
Electricity Usage Natural Gas Other Liquid (non-haz) Electricity Usage Natural Gas Other Liquid (non-haz)