IAC Assessment: MA0779
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0779
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2017
Principal Product Aircraft engine components
NAICS 336412 - Aircraft Engine and Engine Parts Manufacturing
SIC 3724 - Aircraft Engines And Engine Parts
Sales $5,000,000-$10,000,000
# of Employees 27
Plant Area (Sq.Ft.) 18,000
Annual Production 50 Units
Production Hrs. Annual 4,386
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $105,588 779,146 kWh $0.14
Electricity Demand $15,283 1,251 kW-months/year $12.22
Natural Gas $6,790 674 MMBtu $10.07
TOTAL ENERGY COSTS $127,661
RECOMMENDED SAVINGS* $92,646 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,462
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.9113 USE SOLAR HEAT FOR HEAT Savings:
$71,879
Cost:
$609,753
$71,879 528,525 $71,879
528,525
kWh
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$7,670
Cost:
$8,325
$7,670 56,394 $7,670
56,394
kWh
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,745
Cost:
$19,917
$6,745 49,599 $6,745
49,599
kWh
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$3,249
Cost:
$100
$3,249 23,892 $3,249
23,892
kWh
05: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING Savings:
$2,890
Cost:
$7,225
$2,890 21,249 $2,890
21,249
kWh
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$213
Cost:
$200
$213 1,569 $213
1,569
kWh
TOTAL RECOMMENDED Savings:
$92,646
Cost:
$645,520
$92,646 681,228 $92,646
681,228
kWh
TOTAL IMPLEMENTED Savings:
$3,462
Cost:
$300
$3,462 25,461 $3,462
25,461
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage