Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2023 |
Principal Product | Water |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4941 - Water Supply |
Sales | $5,000,000-$10,000,000 |
# of Employees | 10 |
Plant Area (Sq.Ft.) | 27,400 |
Annual Production | 797,766 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $181,429 | 1,231,400 | kWh | $0.15 |
Electricity Demand | $21,601 | 2,501 | kW-months/year | $8.64 |
Electricity Fees | $3,591 | - | $ | - |
Natural Gas | $31,582 | 1,987 | MMBtu | $15.89 |
TOTAL ENERGY COSTS | $238,203 | |||
RECOMMENDED SAVINGS* | $80,838 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $63,886 Cost: $285,949 |
$43,063 | 292,950 | $173 | 20 | $20,650 | - | - | - |
$43,063 292,950 kWh |
$173 20 kW-months/year |
$20,650 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $3,299 Cost: $22,900 |
$(-25,855) | (-175,887) | $(-2,427) | (-281) | - | - | $31,581 | 1,987 |
$(-25,855) (-175,887) kWh |
$(-2,427) (-281) kW-months/year |
- - $ |
$31,581 1,987 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6124 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE |
Savings: $10,616 Cost: $23,709 |
$9,528 | 64,824 | $1,088 | 126 | - | - | - | - |
$9,528 64,824 kWh |
$1,088 126 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $1,302 Cost: $900 |
$1,302 | 8,856 | - | - | - | - | - | - |
$1,302 8,856 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $747 Cost: $550 |
- | - | - | - | - | - | $747 | 47 |
- - kWh |
- - kW-months/year |
- - $ |
$747 47 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $988 Cost: $385 |
$914 | 6,221 | $74 | 9 | - | - | - | - |
$914 6,221 kWh |
$74 9 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $80,838 Cost: $334,393 |
$28,952 | 196,964 | $(-1,092) | (-126) | $20,650 | - | $32,328 | 2,034 | $28,952 196,964 kWh |
$(-1,092) (-126) kW-months/year |
$20,650 - $ |
$32,328 2,034 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |