Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2023
Principal Product Municipal Wastewater Treatment
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales $5,000,000-$10,000,000
# of Employees 7
Plant Area (Sq.Ft.) 215,000
Annual Production 640,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $351,462 2,530,400 kWh $0.14
Electricity Demand $41,784 4,760 kW-months/year $8.78
Natural Gas $33,037 1,933 MMBtu $17.09
TOTAL ENERGY COSTS $426,283
RECOMMENDED SAVINGS* $105,123 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$31,262
Cost:
$30,900
$28,769 206,971 $2,493 284 - - - - $28,769
206,971
kWh
$2,493
284
kW-months/year
-
-
MMBtu
-
-
$
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$29,114
Cost:
$20,600
$26,797 192,782 $2,317 264 - - - - $26,797
192,782
kWh
$2,317
264
kW-months/year
-
-
MMBtu
-
-
$
03: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$24,241
Cost:
$55,000
$22,310 160,500 $1,931 220 - - - - $22,310
160,500
kWh
$1,931
220
kW-months/year
-
-
MMBtu
-
-
$
04: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$11,416
Cost:
$78,169
$6,806 48,962 $1,159 132 - - $3,451 - $6,806
48,962
kWh
$1,159
132
kW-months/year
-
-
MMBtu
$3,451
-
$
05: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING Savings:
$4,461
Cost:
$14,400
$4,110 29,565 $351 40 - - - - $4,110
29,565
kWh
$351
40
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$3,059
Cost:
$800
- - - - $3,059 179 - - -
-
kWh
-
-
kW-months/year
$3,059
179
MMBtu
-
-
$
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,570
Cost:
$2,160
$1,210 8,704 $360 41 - - - - $1,210
8,704
kWh
$360
41
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$105,123
Cost:
$202,029
$90,002 647,484 $8,611 981 $3,059 179 $3,451 - $90,002
647,484
kWh
$8,611
981
kW-months/year
$3,059
179
MMBtu
$3,451
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes