Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2012 |
Principal Product | Circuit board laminaiton |
NAICS | 334418 - Printed Circuit Assembly (Electronic Assembly) Manufacturing |
SIC | 3679 - Electronic Components, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 2,628 Thousand Feet |
Production Hrs. Annual | 7,488 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $568,764 | 7,271,424 | kWh | $0.08 |
Electricity Demand | $192,578 | 17,734 | kW-months/year | $10.86 |
Electricity Fees | $10,250 | - | $ | - |
Fuel Oil #4 | $177,328 | 7,771 | MMBtu | $22.82 |
TOTAL ENERGY COSTS | $948,920 | |||
RECOMMENDED SAVINGS* | $71,446 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,396 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $37,819 Cost: $31,800 |
$31,772 | 406,289 | $6,047 | 557 |
$31,772 406,289 kWh |
$6,047 557 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7314 REDUCE VENTILATION AIR |
Savings: $22,269 Cost: $9,650 |
$18,218 | 232,970 | $4,051 | 373 |
$18,218 232,970 kWh |
$4,051 373 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $4,815 Cost: $4,000 |
$4,815 | 61,568 | - | - |
$4,815 61,568 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,781 Cost: - |
$3,781 | 48,355 | - | - |
$3,781 48,355 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $2,762 Cost: $5,000 |
$2,762 | 35,322 | - | - |
$2,762 35,322 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $71,446 Cost: $50,450 |
$61,348 | 784,504 | $10,098 | 930 | $61,348 784,504 kWh |
$10,098 930 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,396 Cost: $40,800 |
$39,349 | 503,179 | $6,047 | 557 | $39,349 503,179 kWh |
$6,047 557 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |