Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2005 |
Principal Product | Corrugated Cardboard |
NAICS | 322211 - Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 45 |
Plant Area (Sq.Ft.) | 144,000 |
Annual Production | 75,000 Thousand Feet |
Production Hrs. Annual | 6,240 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $234,132 | 4,632,240 | kWh | $0.05 |
Electricity Demand | $87,779 | 10,658 | kW-months/year | $8.24 |
Electricity Fees | $41,908 | - | $ | - |
Natural Gas | $456,777 | 64,398 | MMBtu | $7.09 |
TOTAL ENERGY COSTS | $820,596 | |||
RECOMMENDED SAVINGS* | $118,091 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $57,517 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $28,126 Cost: $1,091 |
- | - | - | - | $28,126 | 3,967 | - | - |
- - kWh |
- - kW-months/year |
$28,126 3,967 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY |
Savings: $20,574 Cost: $30,050 |
- | - | - | - | $20,574 | 3,902 | - | - |
- - kWh |
- - kW-months/year |
$20,574 3,902 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $28,927 Cost: $27,000 |
- | - | - | - | $28,927 | 4,060 | - | - |
- - kWh |
- - kW-months/year |
$28,927 4,060 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,983 Cost: $225 |
- | - | - | - | $2,983 | 421 | - | - |
- - kWh |
- - kW-months/year |
$2,983 421 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $9,790 Cost: $4,360 |
- | - | - | - | - | - | $9,790 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$9,790 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $9,392 Cost: $77 |
$9,392 | 174,564 | - | - | - | - | - | - |
$9,392 174,564 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,896 Cost: $1,074 |
$9,022 | 167,670 | $1,874 | 19 | - | - | - | - |
$9,022 167,670 kWh |
$1,874 19 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $3,882 Cost: - |
$2,667 | 49,555 | $1,215 | 12 | - | - | - | - |
$2,667 49,555 kWh |
$1,215 12 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $3,521 Cost: $4,628 |
$2,892 | 53,741 | $629 | 6 | - | - | - | - |
$2,892 53,741 kWh |
$629 6 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $118,091 Cost: $68,505 |
$23,973 | 445,530 | $3,718 | 37 | $80,610 | 12,350 | $9,790 | - | $23,973 445,530 kWh |
$3,718 37 kW-months/year |
$80,610 12,350 MMBtu |
$9,790 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $57,517 Cost: $35,786 |
$21,081 | 391,789 | $3,089 | 31 | $23,557 | 4,323 | $9,790 | - | $21,081 391,789 kWh |
$3,089 31 kW-months/year |
$23,557 4,323 MMBtu |
$9,790 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |