IAC logo
IAC Assessment: MI0119
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MI0119
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Miami
Assessment Year 2005
Principal Product Adhesive Bandages
NAICS 339113 - Surgical Appliance and Supplies Manufacturing
SIC 3842 - Surgical Appliances And Supplies
Sales $10,000,000-$50,000,000
# of Employees 175
Plant Area (Sq.Ft.) 100,000
Annual Production 24,000,000 Pieces
Production Hrs. Annual 7,200
Location (State) Fl
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $143,506 2,813,706 kWh $0.05
Electricity Demand $49,596 6,009 kW-months/year $8.25
Electricity Fees $13,011 - $ -
TOTAL ENERGY COSTS $274,570
RECOMMENDED SAVINGS* $26,485 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $21,204
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ gal $ lb $ $ $ $
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$9,064
Cost:
$170
$7,139 139,968 $1,925 233 - - - - - - - - $7,139
139,968
kWh
$1,925
233
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
02: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$6,450
Cost:
$96
$3,916 76,776 $2,534 307 - - - - - - - - $3,916
76,776
kWh
$2,534
307
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$4,432
Cost:
$100
- - - - - - - - - - $4,432 - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
$4,432
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,973
Cost:
$862
$3,135 61,472 $1,174 143 - - - - $(-336) - - - $3,135
61,472
kWh
$1,174
143
kW-months/year
-
-
gal
-
-
lb
$(-336)
-
$
-
-
$
05: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$1,003
Cost:
$22
- - - - - - $1,091 21,600 - - $(-88) - -
-
kWh
-
-
kW-months/year
-
-
gal
$1,091
21,600
lb
-
-
$
$(-88)
-
$
06: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$849
Cost:
$769
$849 16,650 - - - - - - - - - - $849
16,650
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
07: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$714
Cost:
$52
$653 12,805 - - $8 8 - - - - $53 - $653
12,805
kWh
-
-
kW-months/year
$8
8
gal
-
-
lb
-
-
$
$53
-
$
TOTAL RECOMMENDED Savings:
$26,485
Cost:
$2,071
$15,692 307,671 $5,633 683 $8 8 $1,091 21,600 $(-336) - $4,397 - $15,692
307,671
kWh
$5,633
683
kW-months/year
$8
8
gal
$1,091
21,600
lb
$(-336)
-
$
$4,397
-
$
TOTAL IMPLEMENTED Savings:
$21,204
Cost:
$1,202
$14,843 291,021 $5,633 683 $8 8 $1,091 21,600 $(-336) - $(-35) - $14,843
291,021
kWh
$5,633
683
kW-months/year
$8
8
gal
$1,091
21,600
lb
$(-336)
-
$
$(-35)
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ lb $ $ $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Administrative Changes