Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2006 |
Principal Product | Asphalt |
NAICS | 324121 - Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951 - Asphalt Paving Mixtures And Blocks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 5,000,000 Tons |
Production Hrs. Annual | 2,000 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $59,905 | 1,149,600 | kWh | $0.05 |
Electricity Demand | $49,215 | 5,935 | kW-months/year | $8.29 |
Electricity Fees | $11,730 | - | $ | - |
Other Gas | $1,863,020 | 931,281 | MMBtu | $2.00 |
TOTAL ENERGY COSTS | $1,983,870 | |||
RECOMMENDED SAVINGS* | $332,807 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Gas | Electricity Usage | Electricity Demand | Other Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY |
Savings: $178,061 Cost: $75,000 |
- | - | - | - | $178,061 | 10,263 |
- - kWh |
- - kW-months/year |
$178,061 10,263 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $145,490 Cost: $5,540 |
- | - | - | - | $145,490 | 3,596 |
- - kWh |
- - kW-months/year |
$145,490 3,596 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,318 Cost: - |
$2,721 | 2,721 | $2,597 | 313 | - | - |
$2,721 2,721 kWh |
$2,597 313 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $1,956 Cost: $5,024 |
$1,526 | 29,289 | $430 | 52 | - | - |
$1,526 29,289 kWh |
$430 52 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,982 Cost: $56 |
$938 | 18,000 | $1,044 | 126 | - | - |
$938 18,000 kWh |
$1,044 126 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $332,807 Cost: $85,620 |
$5,185 | 50,010 | $4,071 | 491 | $323,551 | 13,859 | $5,185 50,010 kWh |
$4,071 491 kW-months/year |
$323,551 13,859 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Gas | Electricity Usage | Electricity Demand | Other Gas |