Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2007 |
Principal Product | Fiberglass boats |
NAICS | 336612 - Boat Building |
SIC | 3732 - Boat Building And Repairing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 420 |
Plant Area (Sq.Ft.) | 1,000,000 |
Annual Production | 2,000 Pieces |
Production Hrs. Annual | 6,600 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $511,908 | 5,747,842 | kWh | $0.09 |
Electricity Demand | $61,927 | 17,950 | kW-months/year | $3.45 |
Electricity Fees | $23,616 | - | $ | - |
TOTAL ENERGY COSTS | $597,451 | |||
RECOMMENDED SAVINGS* | $119,319 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $91,892 Cost: $111,815 |
$85,415 | 1,041,645 | $6,477 | 1,894 |
$85,415 1,041,645 kWh |
$6,477 1,894 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $11,557 Cost: $1,210 |
$8,780 | 107,077 | $2,777 | 812 |
$8,780 107,077 kWh |
$2,777 812 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,187 Cost: $40 |
$1,004 | 12,242 | $183 | 53 |
$1,004 12,242 kWh |
$183 53 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,330 Cost: $1,210 |
$2,198 | 26,804 | $132 | 38 |
$2,198 26,804 kWh |
$132 38 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,639 Cost: $40 |
$1,482 | 18,073 | $157 | 46 |
$1,482 18,073 kWh |
$157 46 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $3,802 Cost: $3,475 |
$3,501 | 42,692 | $301 | 88 |
$3,501 42,692 kWh |
$301 88 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,172 Cost: $1,210 |
$2,069 | 25,225 | $103 | 30 |
$2,069 25,225 kWh |
$103 30 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,540 Cost: $40 |
$1,358 | 16,555 | $182 | 53 |
$1,358 16,555 kWh |
$182 53 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $1,765 Cost: $3,475 |
$1,693 | 20,647 | $72 | 22 |
$1,693 20,647 kWh |
$72 22 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,435 Cost: $1,210 |
$1,279 | 15,600 | $156 | 46 |
$1,279 15,600 kWh |
$156 46 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $119,319 Cost: $123,725 |
$108,779 | 1,326,560 | $10,540 | 3,082 | $108,779 1,326,560 kWh |
$10,540 3,082 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |