Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2013 |
Principal Product | Plastic building Materials |
NAICS | 332312 - Fabricated Structural Metal Manufacturing |
SIC | 3441 - Fabricated Structural Metal |
Sales | $10,000,000-$50,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 85,000 |
Annual Production | 6,000,000 Pounds |
Production Hrs. Annual | 4,992 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $123,363 | 2,543,600 | kWh | $0.05 |
Electricity Demand | $83,981 | 7,184 | kW-months/year | $11.69 |
Electricity Fees | $38,433 | - | $ | - |
TOTAL ENERGY COSTS | $245,778 | |||
RECOMMENDED SAVINGS* | $92,845 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $71,487 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $33,139 Cost: $21,580 |
$20,900 | 435,409 | $12,239 | 1,047 |
$20,900 435,409 kWh |
$12,239 1,047 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $11,581 Cost: $2,980 |
$7,303 | 152,164 | $4,278 | 366 |
$7,303 152,164 kWh |
$4,278 366 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3311 REPLACE DC EQUIPMENT WITH AC EQUIPMENT |
Savings: $10,510 Cost: $12,640 |
$6,629 | 138,216 | $3,881 | 332 |
$6,629 138,216 kWh |
$3,881 332 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $8,487 Cost: $160 |
$5,354 | 111,540 | $3,133 | 268 |
$5,354 111,540 kWh |
$3,133 268 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,459 Cost: $1,660 |
$4,855 | 101,151 | $3,604 | 308 |
$4,855 101,151 kWh |
$3,604 308 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,663 Cost: $560 |
$3,383 | 80,906 | $2,280 | 195 |
$3,383 80,906 kWh |
$2,280 195 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $5,216 Cost: $2,600 |
$3,907 | 81,390 | $1,309 | 112 |
$3,907 81,390 kWh |
$1,309 112 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,961 Cost: $80 |
$3,007 | 62,646 | $1,954 | 167 |
$3,007 62,646 kWh |
$1,954 167 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $4,605 Cost: $5,740 |
$2,449 | 52,464 | $2,156 | 190 |
$2,449 52,464 kWh |
$2,156 190 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $224 Cost: $430 |
$141 | 2,945 | $83 | 7 |
$141 2,945 kWh |
$83 7 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $92,845 Cost: $48,430 |
$57,928 | 1,218,831 | $34,917 | 2,992 | $57,928 1,218,831 kWh |
$34,917 2,992 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $71,487 Cost: $34,720 |
$44,768 | 934,118 | $26,719 | 2,291 | $44,768 934,118 kWh |
$26,719 2,291 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |