IAC Assessment: MI0275
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MI0275
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Miami
Assessment Year 2015
Principal Product Waste Water
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales $10,000,000-$50,000,000
# of Employees 35
Plant Area (Sq.Ft.) 4,014,490
Annual Production 14,600,000 Thousand Gallons
Production Hrs. Annual 8,736
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,238,409 27,735,043 kWh $0.04
Electricity Demand $789,978 71,903 kW-months/year $10.99
Electricity Fees $192,364 - $ -
TOTAL ENERGY COSTS $2,220,751
RECOMMENDED SAVINGS* $130,626 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $130,626
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes
$ kWh $ kW-months/year $ $
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$85,489
Cost:
$171,258
$54,281 1,206,242 $31,208 2,840 - - $54,281
1,206,242
kWh
$31,208
2,840
kW-months/year
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$14,615
Cost:
$840
$10,945 243,215 $3,670 334 - - $10,945
243,215
kWh
$3,670
334
kW-months/year
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$12,526
Cost:
$45,190
$9,384 208,529 $3,142 286 - - $9,384
208,529
kWh
$3,142
286
kW-months/year
-
-
$
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$11,206
Cost:
$18,462
$8,393 186,514 $2,813 256 - - $8,393
186,514
kWh
$2,813
256
kW-months/year
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,264
Cost:
$5,922
$6,264 139,220 - - - - $6,264
139,220
kWh
-
-
kW-months/year
-
-
$
06: 2.7134 USE PHOTOCELL CONTROLS Savings:
$507
Cost:
$360
$507 11,257 - - - - $507
11,257
kWh
-
-
kW-months/year
-
-
$
07: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$19
Cost:
$80
- - - - $19 - -
-
kWh
-
-
kW-months/year
$19
-
$
TOTAL RECOMMENDED Savings:
$130,626
Cost:
$242,112
$89,774 1,994,977 $40,833 3,716 $19 - $89,774
1,994,977
kWh
$40,833
3,716
kW-months/year
$19
-
$
TOTAL IMPLEMENTED Savings:
$130,626
Cost:
$242,112
$89,774 1,994,977 $40,833 3,716 $19 - $89,774
1,994,977
kWh
$40,833
3,716
kW-months/year
$19
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes