IAC Assessment: MI0445
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MI0445
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Miami
Assessment Year 2024
Principal Product Pharmaceuticals
NAICS 325412 - Pharmaceutical Preparation Manufacturing
SIC 2834 - Pharmaceutical Preparations
Sales $100,000,000-$500,000,000
# of Employees 170
Plant Area (Sq.Ft.) 480,000
Annual Production 1,000,000 Pieces
Production Hrs. Annual 8,400
Location (State) PR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $2,852,531 14,191,320 kWh $0.20
Electricity Demand $329,995 34,264 kW-months/year $9.63
Electricity Fees $190,809 - $ -
TOTAL ENERGY COSTS $3,373,335
RECOMMENDED SAVINGS* $837,486 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees
$ kWh $ kW-months/year $ $
01: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$427,475
Cost:
$602,500
$400,084 1,990,468 $27,391 2,844 - - $400,084
1,990,468
kWh
$27,391
2,844
kW-months/year
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$217,248
Cost:
$42,472
$203,331 1,011,598 $13,917 1,445 - - $203,331
1,011,598
kWh
$13,917
1,445
kW-months/year
-
-
$
03: 2.8123 PAY UTILITY BILLS ON TIME Savings:
$80,165
Cost:
-
- - - - $80,165 - -
-
kWh
-
-
kW-months/year
$80,165
-
$
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$46,588
Cost:
$99,444
- - $46,588 4,837 - - -
-
kWh
$46,588
4,837
kW-months/year
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$32,574
Cost:
$11,027
$30,487 151,679 $2,087 217 - - $30,487
151,679
kWh
$2,087
217
kW-months/year
-
-
$
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$19,584
Cost:
$150
- - - - $19,584 - -
-
kWh
-
-
kW-months/year
$19,584
-
$
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$10,583
Cost:
$5,793
$9,905 49,281 $678 70 - - $9,905
49,281
kWh
$678
70
kW-months/year
-
-
$
08: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,269
Cost:
$2,860
$3,269 16,265 - - - - $3,269
16,265
kWh
-
-
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$837,486
Cost:
$764,246
$647,076 3,219,291 $90,661 9,413 $99,749 - $647,076
3,219,291
kWh
$90,661
9,413
kW-months/year
$99,749
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees