IAC Assessment: MO0038
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MO0038
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri, Rolla
Assessment Year 1991
Principal Product PENCILS AND PENS
NAICS n/a
SIC 3951 - Pens And Mechanical Pencils
Sales $10,000,000-$50,000,000
# of Employees 305
Plant Area (Sq.Ft.) 0
Annual Production 16,800,000 Pieces
Production Hrs. Annual 6,120
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $253,305 3,966,002 kWh $0.06
Natural Gas $8,123 1,713 MMBtu $4.74
TOTAL ENERGY COSTS $261,428
RECOMMENDED SAVINGS* $5,483 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,449
Cost:
$357
$1,449 22,567 - - $1,449
22,567
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$283
Cost:
$528
$283 4,396 - - $283
4,396
kWh
-
-
MMBtu
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,080
Cost:
$663
$2,080 32,532 - - $2,080
32,532
kWh
-
-
MMBtu
04: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$1,215
Cost:
$960
$1,215 19,050 - - $1,215
19,050
kWh
-
-
MMBtu
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$344
Cost:
-
$468 7,327 $(-124) (-27) $468
7,327
kWh
$(-124)
(-27)
MMBtu
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$112
Cost:
$320
$112 1,758 - - $112
1,758
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$5,483
Cost:
$2,828
$5,607 87,630 $(-124) (-27) $5,607
87,630
kWh
$(-124)
(-27)
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas